Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

Exin CDCS - EXIN EPI Certified Data Centre Specialist

Page: 1 / 2
Total 60 questions

What is the advantage or disadvantage of using MPO (Multi-fiber Push On)/pre-terminated fiber?

A.

There is no advantage, as it cannot be used with OM4 optical fiber cables.

B.

There is no advantage, as it creates additional heat load in the data center.

C.

It speeds up installation and provides an easy upgrade to transmission speeds up to 40 Gbit/s -100 Gbit/s.

D.

It is a very flexible system as it can be used for both copper cables and optical fiber cables.

You are allowed to use a calculator for this question.

A computer room has a net volume of approximately 2,500 m³ / 88,287 ft³.

The temperature is 20 °C / 68 °F.

The required design concentration is 7%.

The S-Factor is 0.1359 (metric) / 1.885 (imperial).

Calculate the amount of gas required for this computer room based on FM200. What is the correct weight?

A.

Approximately 410 kg / 900 lbs

B.

Approximately 820 kg / 1,800 lbs

C.

Approximately 1,390 kg / 3,000 lbs

D.

Approximately 1,640 kg / 3,600 lbs

A 5kW (power consumption) server keeps crashing with the message 'temperature too high'.

The intake temperature is measured at 25 °C/77 °F and a relative humidity (RH) level of 50%.

The exhaust temperature is 29 °C/84 °F and 45% RH.

The raised floor is providing an adequate amount of CFM/CMH at a reasonable velocity.

The pressure under the raised floor is approximately 25 Pa/0.1 inch Hâ‚‚O.

Analyze the situation and indicate what the most likely cause is for this server to crash.

A.

Dust inside the server causing issues with convection-based heat transfer

B.

The exhaust temperature is exceeding the ASHRAE recommended values

C.

The raised floor pressure is too low and/or the raised floor tile % opening is not adequate

D.

No cause could be determined as the CFM/CMH of the air conditioning equipment is not stated

When are the wet bulb and dry bulb temperatures identical?

A.

When the dry bulb's temperature is at the lowest allowable temperature for IT equipment as per ASHRAE

B.

When the dry bulb's temperature is at the highest allowable temperature for IT equipment as per ASHRAE

C.

When the relative humidity is at the best practice value for relative humidity, being 50% RH

D.

When the relative humidity is 100%

The computer room has high levels of H2S gas contamination. What is the best option to resolve this issue?

A.

Vacuum the whole room using a HEPA/S-Class-based filter.

B.

Install air-scrubbers.

C.

Clean the room and racks with a damp/wet cloth.

D.

Provide more air changes per hour by adding more fresh air to the computer room.

The building in which the computer room is housed is required to have a sprinkler system. The building is therefore equipped with a wet pipe system.

What action, if any, should you recommend for the computer room?

A.

Maintain the current wet pipe system.

B.

Replace the wet pipe system with a deluge system.

C.

Replace the wet pipe system with a dry pipe system.

D.

Replace the wet pipe system with a pre-action system.

What is the main reason to install Earth Leakage protection?

A.

Protection of ICT equipment against high-frequency noise currents

B.

Protection of human lives

C.

Improvement of the data center grounding/earthing system

D.

Protection against lightning strikes

The UPS of a data center, with an ANSI/TIA-942 Rating-4, is installed with the rectifier connected to power feed A and the bypass/reserve line input connected to power feed B.

To which feed will the output of the UPS be synchronized?

A.

The UPS will not synchronize to any of the feeds but use an internal clock to set the output voltage and frequency

B.

Depends on the setting of the UPS, as the UPS can normally be set to either feed

C.

Feed A

D.

Feed B

An MCB needs to be installed in the PDU of an air-conditioner unit.

Which breaking curve should you select?

A.

D-Curve

B.

C-Curve

C.

B-Curve

D.

A-Curve

From the options indicated, what is the correct starting point for the raised floor installation?

A.

Point A

B.

Point B

C.

Point C

D.

Point D