What tools would a project manager use or create to define the project team?

A.

Project schedule, corporate organizational chart, and human resources policy

B.

Work breakdown structure, project organizational chart, and responsibility matrix

C.

Task list, responsibility matrix, and the request for proposal that initiated the project

D.

Project budget, project schedule, and project organizational chart

In relation to establishing a level of acceptable risk, what should you include in your Business Continuity Plan (BCP) to help measure the plan's expected level of success against that level of risk?

A.

Contracted support

B.

Lessons learned

C.

Business analysis

D.

Performance metrics

A project sponsor indicates that a project should build a facility at the lowest cost, in the least time, and with the highest quality. What should the project manager do?

A.

Work with the sponsor to refine the project charter with more feasible constraints

B.

Implement the project with the given constraints, as instructed by the project sponsor

C.

Inform the project sponsor that a lower-quality project will be provided

D.

Inform the project sponsor that the project cannot proceed with the given constraints

How can facilities management improve the sustainability of the building envelope?

A.

Scheduling quarterly inspection of building exterior for structural defects

B.

Increasing efficiency of the central air conditioning chiller plant

C.

Ignore maintenance of the exterior surfaces subject to degradation

D.

Removing shading devices

What budgeting method requires a facility manager to use historical budget data?

A.

Activity-based budgeting

B.

Incremental budgeting

C.

Revenue-based budgeting

What does a Cost Plus to a Guaranteed Maximum Price (GMP) contract signify?

A.

The Contractor is selected based on final drawings and his own costs and the individual subcontractors' costs. No cost increases are allowed beyond the GMP.

B.

The Contractor is selected based on GMP price of the final drawings and can charge the project based on all invoices produced plus its Fee & General Conditions costs.

C.

The Contractor is selected early in the project based on its Fee and its General Conditions costs and provides a GMP once drawings are more developed.

You are the Facility Manager leading a project to integrate two office groups. You will need a unifying message that guides your communications and decision-making when working with a variety of consultants, senior management, and the affected groups. What is your unifying message?

A.

How the project benefits and contributes to the success of the organization.

B.

The needs of the executives who own the project and how they want things done.

C.

How long the project is expected to take, what it will cost, and key parties involved.

D.

Who will be impacted by the project and how their work lives will be improved.

In an indoor office environment, what is the MOST common complaint received by the facilities department?

A.

Indoor air quality

B.

Heating and cooling

C.

Janitorial issues

D.

Ergonomics issues

You are a Facility Manager overseeing a proposed renovation of a floor to meet the needs of the business. What step should be taken first?

A.

Conduct space programming analysis.

B.

Perform a gap analysis.

C.

Engage an architect for scenario alternatives.

D.

Undergo a feasibility study.

What is the process of limiting a company's exposure to liability?

A.

Risk management.

B.

Risk avoidance.

C.

Liability management.

D.

Limited liability analysis.