APICS CPIM-ECO - Execution and Control of Operations

Page: 4 / 4
Total 105 questions

A work center has a balance between the scheduled input and output over the next 4 weeks. One of the three machines in the work center will be out of service for 1 week. Currently, three operators work the first shift, one operator works the second shift, and each has a 40-hour work week. Which of the following actions is best to take to maintain the schedule?

A.

Move an operator from the first to the second shift.

B.

Schedule 40 hours of overtime.

C.

Subcontract 40 hours of work.

D.

Adjust the input.