A company is designing a production process for a new consumer product. To ensure that the product will be traceable from design and production through end-user receipt and use. the company must develop a system for product

A.

review

B.

packaging

C.

identification

D.

storage

If a value assigned to a unit is non-numerical. it is described as

A.

nonconforming

B.

quantitative

C.

variable

D.

qualitative

A way to convince management that a quality improvement program is needed is to present

A.

the number of audit findings the company received from the last audit

B.

the company's performance in terms of quality in comparison with its competitors

C.

die size of the problem in terms of the potential savings and increased profit that can result from fixing it

D.

data on how employees will produce better quality product and services if their pay is increased and their benefits improved

When measurements are taken using a reference scale, such as a pair of calipers, the resulting data are referred to as

A.

classified

B.

attribute

C.

discrete

D.

continuous

A three-level, two-variable, full factorial experiment is to be run. The minimum number of runs will be

A.

6

B.

8

C.

9

D.

18

The holes in this drawing have what kind of tolerance?

The holes in this drawing have what kind of tolerance?

A.

Collateral

B.

Bilateral

C.

Unilateral

D.

Vertical

What is the probability of an item failing in less than 5 hours if it has a constant failure rate of 1/hour?

A.

0.00674

B.

0.99127

C.

0.99326

D.

0.99642

Statistical process control was originated by

A.

Deming

B.

Feigenbaum

C.

Jurau

D.

Shewhart

The primary benefit of implementing a supplier rating system for an organization is to

A.

ensure reduction in the supplier's process variability

B.

help the organization identify supplier’s areas competencies and weaknesses

C.

measure the supplier's timeliness and delivery

D.

guarantee an improvement in the supplier audit

Which of the following symbols represents process performance index?

A.

CP

B.

Cpk

C.

ppk

D.

P