Which of the following is not an example of a typical generic skill required for testing?

A.

Be able to apply test-driven development

B.

Be able to use test management tools and defect tracking tools

C.

Be able to communicate defects and failures to developers as objectively as possible

D.

Possess the necessary social skills that support effective teamwork

A Test Manager conducts risk assessment for a project. One of the identified risks is: The sub-contractor may fail to meet his commitment". If this risk materializes. it will lead to delay in completion of testing required for the current cycle.

Which of the following sentences correctly describes the risk?

A.

It is a product risk since any risk associated with development timeline is a product risk.

B.

It is no longer a risk for the Test Manager since an independent party (the sub-contractor) is now managing it

C.

It is a object risk since successful completion of the object depends on successful and timely completion of the tests

D.

It is a product risk since default on part of the sub-contractor may lead to delay in release of the product

Which ONE of the following statements BEST applies tochecklist-based testing?

A.

Checklists should contain general guidelines to ensure that all aspects of the software are covered.

B.

Checklists should contain specific test conditions that can be individually and directly checked.

C.

Checklists should primarily consist of automated test cases to maximize efficiency.

D.

Checklists should be used exclusively for functional testing, as they are unsuitable for non-functional testing.

Which ONE of the following is a characteristic of exploratory testing?

A.

Effectiveness depends on the individual testers' skills

B.

Usually conducted when there is sufficient time for testing

C.

Test cases are written once the specifications become available

D.

Testing without defined time-boxes

Which ONE of the following options BEST describes thethird test quadrant (Q3)?

A.

This test quadrant contains smoke tests and non-functional tests (except usability tests). These tests are often automated.

B.

This test quadrant is business-facing and criticizes the system. It contains exploratory testing, usability testing, and user acceptance testing.

C.

This test quadrant contains functional tests, examples, user story tests, user experience prototypes, API testing, and simulations. These tests check the acceptance criteria and can be manual or automated.

D.

This test quadrant is technology-facing and supports the team. These tests should be automated and included in the continuous integration (CI) process.

Pariksha labs is a mature software testing company. They are TMMi level 5 certified. Their testing processes are well defined. Which ONE of the following statements is likely to be CORRECT about them?

A.

The company uses same test strategy for all the projects doing minor changes based on test manager responsible for the project because their test strategy template is very mature and do not need to change

B.

The question about the test design techniques to be used is determined based on various factors such as the domain and expectations of the stakeholders

C.

Same set of testing processes are used by them without needing any tweaks because that is the hallmark of a mature testing company.

D.

They try to perform 100% automation for every project because automation is a must for efficiency

Which of the following is a test-first approach, where tests that express a shared understanding from stakeholders of how the application is expected to work, are first written in business-readable language (following the Given/When/Then format), and then made executable to drive development?

A.

Test-Driven Development (TDD)

B.

Acceptance Test-Driven Development (ATDD)

C.

Behavior-Driven Development (BDD)

D.

Domain-Driven Design (DDD)

An agile software development organization has recently hired a senior tester. The organization has distributed teams spread across time zones. They need to share test status with various stakeholders including upper management and customers at a regular interval. Which of the following statements seems to be correct with regards to the communication?

A.

Since the stakeholders include upper management, formal reports delivered face-to-face are critical.

B.

Distributed nature of teams working in various time zones means email communication will work better.

C.

Agile nature of the project means very less documentation and hence the status need not be documented and shared in a formal manner

D.

Since the stakeholders include customers frequent informal communication without a specific frequency works better.

Test automation allows you to:

A.

demonstrate the absence of defects

B.

produce tests that are less subject to human errors

C.

avoid performing exploratory testing

D.

increase test process efficiency by facilitating management of defects