A customer does NOT want the basis to be prorated. In the employee history data file, what dates must the customer enter?

A.

Dates later than program dates

B.

Dates should NOT be entered

C.

Dates equal to the program dates

D.

Dates earlier than program dates

What does the Enable Guideline Optimization setting do? Note: There are 2 correct answers to this question.

A.

It helps render the worksheet faster when there are more than 1,000 guideline formulas.

B.

It changes the guidelines so they are updated on the form immediately.

C.

It requires relaunching the form when guidelines are changed during mid-cycle.

D.

It locks the guideline rule settings so they are un-editable after form launch.

Which scenario requires the weights and mappings data file to be reimported?

A.

Change in business goal name

B.

Change in eligibility rule criteria

C.

Update in an employee’s assignment date

D.

Update in bonus cap

In which customer scenarios are multiple bonus plans required in a single program? Note: There are 2 correct answers to this question.

A.

The bonuses of different groups of employees are affected by different business goals.

B.

There is a single business goal applied to Manufacturing and Engineering, but HR is excluded from the bonus process.

C.

There are only two business goals, but the weighting of the goals varies by employee grade.

D.

In some countries, the bonus is multiplicative, while in others it is additive.

How do you ensure that a planner enters an amount within a specific range?

A.

Enter values in the minimum/maximum columns on the business goals file.

B.

Configure minimum/maximum guidelines in the plan setup.

C.

Create gates using performanceMin and performanceMax.

D.

Set min-max to display as guideline pattern.

What is the effect of proration rounding?

A.

Rounds proration to a monthly value

B.

Changes start and/or end date used in BonusCalculation

C.

Forces proration to have X decimal places, where X is configurable

D.

Allows for the use of "point in time" salary calculations

Which of the following can be achieved using variable pay gates? Notes: There are 2 correct answers to this question.

A.

There are three business goals: Revenue, EBITDA, and Customer Satisfaction. The Individual section is capped to 100% unless the combined payout of the business goals exceeds 75%.

B.

There are three business goals: Revenue, EBITDA, and Customer Satisfaction. The entire business goal section will pay out at 50% unless Customer Satisfaction is above target.

C.

There are three business goals: Revenue, EBITDA, and Customer Satisfaction. The EBITDA goal CANNOT pay more than 100% unless Revenue achieves above target.

D.

There are three business goals: Revenue, EBITDA, and Customer Satisfaction. The EBITDA goal will payout at 0% unless the Individual performance rating is "Good" or better.

From where can you pull fields to assign business goals to employees through the business goals import file?

A.

Summary level custom reportable fields

B.

Bonus plan weights

C.

Summary level standard fields

D.

Employee history fields

Your client wants to change the label on a field in the Assignment Details level of their worksheet. Where could you make the change? Note: There are 2 correct answers to this question.

A.

Column Designer, Entry Level fields

B.

Column Designer, Assignment Level fields

C.

Custom Views

D.

Employee History background element

In which ways can the basis be configured in a non-EC integrated plan? Note: There are 2 correct answers to this question.

A.

Imported from bonus plan

B.

Imported from goal management

C.

Imported from employee history

D.

Imported from user data file