Which scenario does not allow you to access the project team of the higher-level WBS element during “workforce planning”?

Please choose the correct answer.

Response:

A.

If a WBS element does not have its own project team

B.

If a WBS element does have its own project team

C.

WBS element is in the higher level

D.

Project team is in the higher level in hierarchy to WBS element

Which statements about project coding mask are true?

There are 3 correct answers to this question.

Response:

A.

You must always use a project coding mask for your projects.

B.

The project coding mask can begin with a numerical key.

C.

The project coding mask can be shortened later, even if projects have already been created with this project coding mask.

D.

In project number maintenance, special characters are automatically determined using the project coding mask.

E.

You can lock a project coding mask for standard projects or operative projects.

You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason?

Please choose the correct answer.

Response:

A.

The control key is set to no scheduling.

B.

The scheduling type is set to capacity requirements only.

C.

The normal duration of each activity is missing.

D.

There is a loop in the network.

Which of the following are used when you use the SAP Document Management System in Project System to assign document info records?

There are 2 correct answers to this question.

Response:

A.

WBS elements

B.

Activities

C.

Milestones

D.

Structures

Which of the following specifies how much time must elapse between individual archiving steps in network type?

Please choose the correct answer.

Response:

A.

Functional areas

B.

Residence times

C.

Classification indicator

D.

Functional areas

Which of the following decides whether networks can be header assigned or activity-assigned?

There are 2 correct answers to this question.

Response:

A.

Order type

B.

Plant

C.

Billing type

D.

Network structure

What are the pre-requisites for distributing work to HR Resources?

There are 2 correct answers to this question.

Response:

A.

In Customizing for the Project System, you must have defined profiles for workforce planning in Resources.

B.

Assigned work centers to the internally processed activities.

C.

Assigned one or more labor capacity to a work center.

What is the starting point for milestone billing?

Please choose the correct answer.

Response:

A.

Purchase requisition

B.

Purchase order

C.

Goods receipt

D.

Sales order item with a billing plan

Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed?

Please choose the correct answer.

Response:

A.

Cost indicators

B.

Project cost indicators

C.

Operative indicators

D.

Billing indicators

Which method of revenue planning allows you to follow the same procedure as in hierarchical cost planning or can be entered by revenue element?

Please choose the correct answer.

Response:

A.

Manual planning in billing elements in the project structure

B.

Sales order planning

C.

Billing plan in project billing elements

D.

Hierarchical billing plan