Assume a scenario where in, during the planning phase you entered basic dates for WBS elements, for instance by creating graphical time bars in the project planning board and as a result in the execution phase you have an option to set the actual dates in the sameway in the project planning board.

What is the status that must be set before you can enter actual start and actual end dates?

There are 2 correct answers to this question.

Response:

A.

Partially released

B.

Released

C.

Partially set

D.

Partially finished

When using networks and activities, planned costs are automatically calculated based on the resource requirements identified for which of the following?

There are 2 correct answers to this question.

Response:

A.

Tasks

B.

WBS

C.

Activities

D.

Operations

Which of the following determines the item category assigned in the sales documents?

There are 2 correct answers to this question.

Response:

A.

Sales document type

B.

Schedule line items

C.

Material pricing group

D.

Material item category group

A customer wants to maintain basic data and dates of a WBS element on the same tab. Also, basic start and basic finish should be mandatory fields. What do you recommend?

There are 2 correct answers to this question.

Response:

A.

Define Layout Detail Screen for WBS to specify customer-specific tabs.

B.

Define Create User-Defined Fields for WBS to specify the mandatory fields.

C.

Define Field Selection for WBS to specify the mandatory fields.

D.

Define Table Settings for WBS to specify customer-specific tabs.

Which technique is one of the ways to measure the earned value where each milestone corresponds to a percentage of work completed in an activity or a WBS element in progress analysis?

Please choose the correct answer.

Response:

A.

Trend technique

B.

Project technique

C.

Milestone technique

D.

Period indicator technique

Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning?

Please choose the correct answer.

Response:

A.

Control key

B.

Confirmation key

C.

Scheduling key

D.

Customizing key

Which type of confirmation allows you to enter the actual start and finish date,forecast finish date and forecast work in a tabular format?

Please choose the correct answer.

Response:

A.

Individual confirmation

B.

Single confirmation

C.

Collective confirmation

D.

Group confirmation

What does ‘E’ determine in account assignment while using consumption posting indicator to determine the controlling object for the sales item?

Please choose the correct answer.

Response:

A.

E determines that the sales order is a controlling object

B.

E determines that the sales order is a project is a controlling object

C.

E determines that the sales order items are relevant for delivery through sales and distribution

D.

E determines that the sales order is a cost object

Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element.

Which of the following costs can be planned?

There are 3 correct answers to this question.

Response:

A.

Cost element level

B.

Each material

C.

Each internal activity

D.

Internal service

Which costing supplies strategic information that can be used to reduce overheads and increase profitability by highlighting unprofitable products or customers?

Please choose the correct answer.

Response:

A.

Overheads costing

B.

Planned costing

C.

Profitability costing

D.

Activity based costing