SAP C_TPLM22_67 - SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7
Assume a scenario where in, during the planning phase you entered basic dates for WBS elements, for instance by creating graphical time bars in the project planning board and as a result in the execution phase you have an option to set the actual dates in the sameway in the project planning board.
What is the status that must be set before you can enter actual start and actual end dates?
There are 2 correct answers to this question.
Response:
When using networks and activities, planned costs are automatically calculated based on the resource requirements identified for which of the following?
There are 2 correct answers to this question.
Response:
Which of the following determines the item category assigned in the sales documents?
There are 2 correct answers to this question.
Response:
A customer wants to maintain basic data and dates of a WBS element on the same tab. Also, basic start and basic finish should be mandatory fields. What do you recommend?
There are 2 correct answers to this question.
Response:
Which technique is one of the ways to measure the earned value where each milestone corresponds to a percentage of work completed in an activity or a WBS element in progress analysis?
Please choose the correct answer.
Response:
Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning?
Please choose the correct answer.
Response:
Which type of confirmation allows you to enter the actual start and finish date,forecast finish date and forecast work in a tabular format?
Please choose the correct answer.
Response:
What does ‘E’ determine in account assignment while using consumption posting indicator to determine the controlling object for the sales item?
Please choose the correct answer.
Response:
Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element.
Which of the following costs can be planned?
There are 3 correct answers to this question.
Response:
Which costing supplies strategic information that can be used to reduce overheads and increase profitability by highlighting unprofitable products or customers?
Please choose the correct answer.
Response: