Can the user status forbid business transactions that the system status allows?

Please choose the correct answer.

Response:

A.

No, user status can only create a warning.

B.

Yes, by creating an appropriate status profile.

C.

Yes, if the status number of the user status is defined with higher priority.

D.

No, system status has a higher priority than user status.

In which check does only receipts that are booked before a requirement (issue) are included in the check for this issue?

Please choose the correct answer.

Response:

A.

Available to promise check

B.

Available on booking check

C.

Available on requirement check

D.

Immediate delivery check

Among the various functions provided by progress tracking that simplify data entry and analysis which function allows you to go the master data display for objects that are underlined?

Please choose the correct answer.

Response:

A.

Mass change of scenarios

B.

Copying dates

C.

Subitems

D.

Hotspots

Which of the following levels can you assign persons to work centers?

There are 2 correct answers to this question.

Response:

A.

Workforce planning level

B.

Assignment level

C.

Capacity category level

D.

Work center level

In which of the following levels can you execute BOM transfer in the order browser?

There are 3 correct answers to this question.

Response:

A.

For multiple assemblies

B.

For the whole multi-level BOM for a sales order item

C.

For a sub-tree

D.

For an individual assembly

Based on which of the following; reservations or purchase requisitions can automatically be created for a project?

There are 2 correct answers to this question.

Response:

A.

WBS element

B.

Internal service planning

C.

External service planning

D.

Material

Which business functions from the following are supported by network activities?

There are 3 correct answers to this question.

Response:

A.

Billing plans

B.

Internal activity

C.

External activity

D.

Periodic processing

Which of the following can be used to calculate and update interest in SAP project system?

There are 2 correct answers to this question.

Response:

A.

Planned interest calculation

B.

Actual interest calculation

C.

Compound interest calculation

D.

Result analysis

How can the capacity requirements of an activity be reduced?

There are 3 correct answers to this question.

Response:

A.

With partial confirmations of the activity

B.

By transferring the working times for the activity that was entered in CATS (Cross-Application Time Sheet)

C.

With the period-end closing

D.

By setting the status locked account assignment

E.

With the final confirmation of the activity