An activity-relationship-activity path is cyclical and you are not able to schedule the network. Which analysis tool enables you to detect cyclical relationships and correct them?

Please choose the correct answer.

Response:

A.

Activity analysis tool

B.

Relationship analysis tool

C.

Cycle analysis tool

D.

Loop analysis tool

What are the components on which reporting is based upon, in profit center accounting?

There are 2 correct answers to this question.

Response:

A.

Cost centers

B.

Cost elements

C.

Profit centers

D.

Profit center hierarchy

Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity?

There are 3 correct answers to this question.

Response:

A.

Scheduling must have been carried

B.

A distribution key must be maintained in the work center

C.

A work center must be maintained in the activity

D.

The capacity requirements indicator must not be set in the network header

You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined.

What are the possible reasons for this?

There are 2 correct answers to this question.

Response:

A.

A work center has not been assigned to the activity.

B.

The work center does not contain any available capacity data.

C.

The wrong activity type category is entered in the activity.

D.

The indicator calculate capacity requirements is deactivated in the header of the network.

What is the transaction code for editing the planning profile?

Please choose the correct answer.

Response:

A.

OPSS

B.

OPDS

C.

OPSB

D.

OPSC

Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing?

There are 2 correct answers to this question.

Response:

A.

Activate milestone functions.

B.

Activate indicator sales document date for milestones.

C.

Create a billing plan assigned to a sales order item.

D.

Set up percentage of completion for milestones.

E.

Create a billing plan assigned to a WBS element.

Which item category do you choose if you do not want to include the components in inventory management but want to use them immediately in the network?

Please choose the correct answer.

Response:

A.

Stock item

B.

Network item

C.

Non-stock item

D.

Procurement item

To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?

There are 2 correct answers to this question.

Response:

A.

Billing element

B.

Cost element

C.

Pricing element

D.

Account assignment element

Which function of budgeting allows you to transfer any funds not used up in the previous fiscal year to the budget of the new fiscal year?

Please choose the correct answer.

Response:

A.

Budget release function

B.

Budget carry forward function

C.

Budget transfer function

D.

Budget Return function

When using budgeting and active availability control, which business transactions affect the current budget?

There are 3 correct answers to this question.

Response:

A.

Cost element planning

B.

Original budget

C.

Revenues

D.

Transfers

E.

Supplements