SAP C_TPLM22_67 - SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7
An activity-relationship-activity path is cyclical and you are not able to schedule the network. Which analysis tool enables you to detect cyclical relationships and correct them?
Please choose the correct answer.
Response:
What are the components on which reporting is based upon, in profit center accounting?
There are 2 correct answers to this question.
Response:
Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity?
There are 3 correct answers to this question.
Response:
You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined.
What are the possible reasons for this?
There are 2 correct answers to this question.
Response:
What is the transaction code for editing the planning profile?
Please choose the correct answer.
Response:
Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addition to enable milestone billing?
There are 2 correct answers to this question.
Response:
Which item category do you choose if you do not want to include the components in inventory management but want to use them immediately in the network?
Please choose the correct answer.
Response:
To link customer inquiry in SD to the project system, you need to assign one or more inquiry items to which of the WBS element?
There are 2 correct answers to this question.
Response:
Which function of budgeting allows you to transfer any funds not used up in the previous fiscal year to the budget of the new fiscal year?
Please choose the correct answer.
Response:
When using budgeting and active availability control, which business transactions affect the current budget?
There are 3 correct answers to this question.
Response: