Which statement is valid regarding networks?

A.

A network activity can be assigned to several WBS elements

B.

Material components can be assigned to activity elements

C.

Relationships can be used to connect activities of different networks

D.

A network can be activity-account-assigned and header-account-assigned

You want to determine the planned costs for an internally processed activity. Which data do you need Note: There are 2 correct answers to this question

A.

Duration

B.

Activity type

C.

Work

D.

Profit center

An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

A.

The network profile

B.

The control key

C.

The table of MRP controllers

D.

The scheduling parameters for the network

Resources

How can you define external task in your project.

Note : there are 2 correct answers for this question.

A.

Assign a purchase order for external processing to the project definition.

B.

Create an external activity in a network.

C.

Create a service milestone.

D.

Create a service activity in a network.

Which report can use user-specific layouts?

A.

Line item report

B.

Enhanced individual overview

C.

Cost element report

D.

Hierarchical report

A customer needs to analyze the capacity requirements of their network activities. Which reports doyou recommend? Note: There are 2 correct answers to this question

A.

Resource reports

B.

Cost element reports

C.

Structure information system reports

D.

Hierarchical reports

A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question

A.

The network activity is assigned to a WBS element

B.

The network is assigned to a sales order item

C.

The material master of the component must permit project stock management

D.

The Project Stock indicator is set in the project definition (non-valuated or valuated)

E.

A procurement indicator must be assigned to the activity

Which object is used to allocate the costs from a claim to the project structure?

A.

Network activity

B.

Internal order

C.

Claim

D.

WBS element

How can you confirm the working hours of different work centers for a single activity?

A.

Create multiple confirmations for the activity and use the appropriate work center for each confirmation

B.

Enter direct activity allocation assigning multiple work centers

C.

Enter multiple work centers within a single confirmation

D.

Assign multiple work centers to the activity

You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget

A.

Results analysis

B.

Easy Cost Planning

C.

Cost forecast

D.

Availability control