Cost & Budget.

A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?

A.

Settlement rules

B.

Costing Sheet

C.

Investment profile.

D.

Results analysis key

When you create a service activity in your network, what data can be entered? Note: There are 3 correct answers to this question.

A.

Service specification

B.

Overall limit (maximum value of all unplanned services)

C.

Service purchase order number

D.

Material master within service specification

E.

Vendor

You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question

A.

The formula for costing in the work center is incorrect

B.

The activity output price for the activity type and cost center assigned to the work center is not maintained.

C.

The duration is missing in the activity

D.

The Determine Costs indicator in the network header rules out planned cost calculation

E.

Integrated planning for the network is active

Resources

How are capacity requirements determined?

A.

Independent of scheduling and according to the capacity planner group.

B.

Using scheduling and the capacity category.

C.

Using the control key of an activity.

D.

Using scheduling and distribution key.

Materials

Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set

of dates that can be scheduled.

Which set of dates can be used for scheduled for network?

Note : there are 2 correct answer for this question.

A.

Planned dates

B.

Fundamental dates

C.

Basic dates

D.

Baseline dates

E.

Forecast dates

Resources

Which of the following transactions can you use to post actual cost for external processing.

Note : there are 2 correct answer for this question.

A.

Approval of a service entry sheet

B.

Posting a goods receipt

C.

Creating a service entry sheet

D.

Approval of a good receipt.

E.

Creating a purchase order.

Which of the following is visible in the project planning board? Note: There are 2 correct answers to this question

A.

Project-relevant purchase orders

B.

Capacity requirements

C.

Maintenance orders assigned to an activity

D.

Production orders assigned to WBS elements

Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?

A.

Set up the requirement date aligned with the activity finish date and an offset of 15 days.

B.

Set up the requirement date manually as February 5.

C.

Set up the requirement date aligned with the activity start date and an offset of 5 days

D.

Set up the requirement date aligned with the activity start date and a negative offset of 5 days

Project Structure

You plan double the work on each internal activity for multiple project. What do you recommend?

A.

Use mass change (CNMASS) in the project system.

B.

Double the work of each internal activity, one after another, in the project Builder.

C.

Double the capacity in the work center.

D.

Use mass change within the project Builder (CJ20N).

What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question

A.

A delivery document type must be configured

B.

A sold to party is necessary

C.

A shipping point is necessary

D.

A sales order must be created in advance