SAP C_TS422_2021 - SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing

Page: 2 / 3
Total 82 questions

Your proyect team decides to use a make-to-order planning strategy for strategic in discrete manufacturing. What is the impact of this decision?

A.

Net requirement calcualtion is sales-order specific.

B.

A sales-order-specific planning run is required.

C.

Storage location MRP areas are required.

D.

Production orders specific stock is created

You need to model goods receipt processing time in detailed scheduling. Whic modeling options do you have?

A.

Model a transportation resorce in the location master.

B.

Model a seperate resource in the production data structure.

C.

Model a resource inbound in the location master.

D.

Model a handling resource in the location master and goods receipt time in the material master.

You set up a material as a phantom assembly by entering the special procurement key in the material master. How can you switch off the phantom assembly in a specific bill of material (BOM)?

A.

Change the special procurement key of the phantom assembly in the BOM.

B.

Change the explosion type of the phantom assembly in the BOM.

C.

Change the phantom item indicator for the phantom assembly in the BOM.

D.

Change the item category of the phantom assembly in the BOM.

You are working with planning strategy 40 (Planning-with-final assembly)

When does consuption of planned independent requirements take places?

A.

When you deliver a sales order

B.

When the MRP result are saved

C.

When you create a sales order

D.

When you create a planned order

For what production type are production orders used?

A.

Process manufacturing processes

B.

Replenishment controlled by control cycles

C.

Discrete manufacturing processes

D.

Period and quantity-oriented production

Which SAP solutions support the supplier area in the portfolio of the Digital Value Network?

A.

SAP Ariba

B.

SAP Hybris

C.

SAP Concur

D.

SAP Fieldglass

E.

SAP SuccessFactors

What does it mean for the production planner when MRP works with infinite capacities?

A.

MRP assigns capacity requirements automatically after the last scheduled order on a work center.

B.

MRP creates capacity requirements without checking the capacity of a work center.

C.

MRP assigns capacity requirements automatically to work center is with the earliest available capacity.

D.

MRP creates capacity requirements only if the work center has sufficient capacity.

Why would you use phantom assemblies?

A.

To simplify the structure of bills of materials

B.

To make the assignment of components easier

C.

To reduce the number of changes required in bills of materials

D.

To reduce the number of material masters

E.

To increase the number of planning levels

Where do you maintain the work center that represents the production line for repetitive manufacturing?

A.

Production version

B.

Routing

C.

Repetitive manufacturing profile

D.

Production cost collector

Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing?

A.

Run MRP with quota arrangement.

B.

Run MRP with automatic selection of production version.

C.

Assign planned orders manual lying the planning table.

D.

Run PP/DS heuristics for repetitive manufacturing.