SAP C_TS422_2022 - SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing

Page: 2 / 3
Total 80 questions

What could be the reason for multiple commitments, where several operations have the same scheduled dates on a work center after dispatching?

Note: There are 2 correct answers to this question.

A.

The Finite Scheduling indicator is NOT set in the strategy profile.

B.

The work center has several individual capacities

C.

The Change Planning Direction indicator is set in the strategy profile

D.

Alternative work centers are fully occupied.

You need to model goods receipt processing time in detailed scheduling. Which modeling options do you have?

Note: There are 3 correct answers to this question.

A.

Model a separate resource in the production data structure.

B.

Model a handling resource in the location master.

C.

Model a transportation lane and carrier selection in the location master.

D.

Model a separate inbound resource in the location master.

E.

Model a goods receipt time in the material master.

where does the system check master data selection settings during the creation of planned orders and production orders?

Note: There are 3 Correct answers to this question.

A.

in the bill of material (BOM)

B.

in the work centers

C.

in the MRP controller

D.

In the routing

E.

in the production version

Which of the following processes lead to an entry in the MRP planning file?

Note: There are 3 correct answers to this question.

A.

Changing the storage bin in warehouse management

B.

Changing the procurement type in the product master

C.

Changing the operation times in the production data structure

D.

Changing the stock in inventory management

E.

Changing the purchasing contract in materials management

which actions does the system perform by default when you save a confirmation for a finished

product in repetitive manufacturing?

Note: There are 3 Correct answers to this question.

A.

Posting of production costs to the production cost collector

B.

posting of goods receipt for the product

C.

Reduction of associated capacity requirements

D.

Archiving of document for assembly scrap

E.

Material staging for next order in sequence

in your Plant, MRP is activated.

which options do you have to exclude a material from the MRP run?

Note: there are 2 correct answers to this question.

A.

Use a specific material status

B.

Use a specific material group

C.

Use a specific MRP type

D.

Use a specific MRP list

What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.

A.

Order type

B.

Planning strategy

C.

Requirements profile

D.

Requirements type

Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA?

Note: There are 2 correct answers to this question.

A.

Order (pool) chart

B.

Capacity requirements chart

C.

Work center capacities chart

D.

Orders (dispatched) chart

Your company produces a finished good based on a forecast and expects it to be in stock when customers order it. If customers order more than the forecasted quantity, this must NOT have any impact on the production program. Which planning strategy do you use?

A.

Make-to-stock production (10)

B.

Planning with final assembly (40)

C.

Make-to-stock production (20)

D.

Planning without final assembly (50)

Which time elements are relevant for lead time scheduling of a production order? Note:

There are 2 correct answers to this question.

A.

setup time

B.

Opening Period

C.

Float after Production

D.

Total replenishment lead time