SAP C_TS422_2022 - SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing
What could be the reason for multiple commitments, where several operations have the same scheduled dates on a work center after dispatching?
Note: There are 2 correct answers to this question.
You need to model goods receipt processing time in detailed scheduling. Which modeling options do you have?
Note: There are 3 correct answers to this question.
where does the system check master data selection settings during the creation of planned orders and production orders?
Note: There are 3 Correct answers to this question.
Which of the following processes lead to an entry in the MRP planning file?
Note: There are 3 correct answers to this question.
which actions does the system perform by default when you save a confirmation for a finished
product in repetitive manufacturing?
Note: There are 3 Correct answers to this question.
in your Plant, MRP is activated.
which options do you have to exclude a material from the MRP run?
Note: there are 2 correct answers to this question.
What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.
Which chart types does the tabular planning table for capacity planning provide in SAP S/4HANA?
Note: There are 2 correct answers to this question.
Your company produces a finished good based on a forecast and expects it to be in stock when customers order it. If customers order more than the forecasted quantity, this must NOT have any impact on the production program. Which planning strategy do you use?
Which time elements are relevant for lead time scheduling of a production order? Note:
There are 2 correct answers to this question.