Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA. When can you use mode selection?

A.

When multiple production versions are maintained for one product

B.

When multiple operations are maintained for one product

C.

When alternative resources are used within one operation

D.

When multiple planned orders exist on one resource

Your project uses process orders for the production of liquid chemicals. What can you define to ensure that production flow only happens in suitable and physically connected tanks? Note: There are 2 correct answers to this question.

A.

Resource matrix

B.

Resource network

C.

Resource hierarchy

D.

Resource selection

You use planning strategy Finite Scheduling with Reverse and want to allow scheduling the past. How can you parameterize this in the strategy profile?

A.

Specify a negative planning horizon.

B.

Specify a positive planning horizon.

C.

Specify a positive offset time.

D.

Specify a negative offset time.

Which of the following elements does MRP take into account during net requirement

calculation? Note:

There are 2 correct answers to this question.

A.

Forecast key figures

B.

Safety Stock

C.

Maximum stock level

D.

Purchase orders

What is the difference between co-products and by-products?

A.

Only co-products are identified by a special item category in the bill of material (BOM)

B.

Only co-products can be manufactured in isolation from the main product

C.

Only co-products have a zero inventory valuation

D.

Only co-products appear in the process or production order settlement rule

Which materials have a negative quantity in a bill of material or in a recipe?

Note: There are 3 correct answers to this question

A.

Continuous flow materials

B.

Bulk materials

C.

By-products

D.

Co-products

E.

Waste products

You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

A.

Kanban

B.

Material requirements planning

C.

Backflushing

D.

Production order release

Which of the following questions do you have to answer before you start creating a bill of material (BOM)?

A.

Is the material type allowed in the BOM?

B.

Which base unit of measure does the material have?

C.

What status does the BOM have?

D.

In which storage location is the BOM required?

What does a line hierarchy in repetitive manufacturing represent?

A.

A production line with more than one work center

B.

A production line with prioritized work centers

C.

A production line with a parallel sequence in the routing

D.

A production line with an alternative sequence in the routing

Which time elements does MRP consider in backward scheduling to determine the order dates for components from dependent requirements?

Note: There are 2 correct answers to this question

A.

Total replenishment lead time

B.

Operation duration

C.

Planned delivery time

D.

In-house production time