Which of the following is the procedure for replacing a damaged UPS power module onsite?

A.

â‘ â‘¢

B.

â‘ â‘£

C.

â‘¡â‘¢

D.

â‘¡â‘£

What are the colors of indicators on the LCD panel of the MDU?

A.

Yellow

B.

Green

C.

Red

D.

Orange

Which of the following statements is false about how to start an electric heater?

A.

If "Dehumidification & Low temperature heating" is selected, the electric heater determines whether to start based on the temperature requirements when the dehumidification or heating conditions are met.

B.

When "Dehumidification heating" is selected, the electric heater determines whether to start based on the current temperature only when the dehumidification function is enabled.

C.

When "Dehumidification heating", "Low temperature heating", or "Dehumidification & Low temperature heating" is selected, if the temperature in the equipment room is low, the air conditioner automatically starts the heating function to meet the temperature control requirements of the equipment room.

D.

When "Low temperature heating" is selected, the electric heater determines whether to start only based on the temperature requirements no matter whether the dehumidification function is enabled.

During routine maintenance of the lithium battery cabinet, which of the following procedure is true about replacing a faulty battery module?

A.

1-6-3-2-5-7-4

B.

1-3-2-6-5-7-4

C.

1-6-2-5-3-7-4

D.

1-2-3-6-5-7-4

After replacing the fan, choose "Menu > _____ > Performance Maintenance" on the main screen to enter the "Performance Maintenance" screen and clear the accumulated runtime of the indoor fan.

A.

Alarms

B.

Settings

C.

Running

D.

Maint

The NetEco supports manual backup and automatic backup.

A.

True

B.

False

Which of the following statements are true?

A.

When the UPS works in normal mode, you can directly turn on the maintenance bypass switch.

B.

When the UPS works in static bypass mode, if the mains input outage occurs suddenly, the UPS automatically switches to battery mode.

C.

Huawei UPS5000-H is a modular UPS. If a module fails, it can be replaced online.

D.

When mains and bypass input of the UPSs share one power source, if mains outage occurs, the UPS cannot work in bypass mode.

Which of the following are the user roles of Power Partner?

A.

Service manager of a rep office

B.

Startup engineer

C.

Inventory operations manager

D.

Project manager

E.

DOC

F.

Service engineer

If a component runtime overdue alarm is generated for an air conditioner, you can clear the device running time on the "Maint > Performance Maintenance" screen.

A.

True

B.

False

The software installation package does not need to be downloaded for the preinstalled server.

A.

True

B.

False