IIBA IIBA-AAC - IIBA Agile Analysis Certification
Backlog items that are dependent on other backlog items compromise and limit rapid decision making, fast delivery and strategic alignment by not leveraging:
At the Strategy Horizon, effective analysis work can help stakeholders make sound decisions by:
When teams use relative estimating, an important outcome of this technique is:
A user story is clear and well-written, but there is broad disagreement amongst development team members about the estimate for the story. The team elects to assign one member for 4 hours to investigate what is really required to deliver this item. This activity the team has chosen is called a:
Planning horizons are important because they allow an organization to:
Strategic decision makers are considering large amounts of complex information covering many different areas. To reduce the information to a manageable level of complexity, they decide to use the following:
The team is using Personas to model customer needs and experiences. They are most likely working in the following horizon?
While discussing the initiative, the team considers cancelling the remaining work. This is an example of the following agile business analysis principle:
When decomposing stories, the concept of “breadth before depth†signifies progressively breaking down:
Working at the Strategy Horizon, the team uses analysis techniques to understand the creation of value propositions for various customer segments. This allows the team to streamline the initiatives and is an example of the following agile business analysis principle: