BCS ISEB-PM1 - BCS Foundation Certificate in IS Project Management
The project management office is worried about the quality of the company's various projects. They want to know which projects are having problems and which ones are doing well.
If the PMO receives the following information, which project should they be the MOST concerned about?
By which process may an unsuccessful supplier seek remedy for unjust awards?
Regardless of style, what information is shown in a process flowchart?
Which of the following correctly explains the term "progressive elaboration"?
In which type of organization(s) is the project manager's role most likely part-time?
Company expenses such as auditing costs, supervision, office supplies, building rent and maintenance are elements of the:
Final product transition is an output of which process?
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
What is the number of stakeholders, if the project has 28 potential communication channels?
If two events cannot both occur in a single trial, they are:
Cost baseline is an output of which of the following processes?
An activity that consumes no time or resources and shows only that a dependency exists between two activities is called:
What is included in a control chart?
Which document contains initial requirements that satisfy stakeholders' needs and expectations?
You are a project manager for Giraffe Enterprises. You've recently taken over for a project manager who lied about his PMI certification and was subsequently fired. Unfortunately, he did a poor job of scope definition.
Which of the following could happen if you don't correct this?