Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
Your team is split between two buildings on either side of town. As a result, the team isn't very cohesive because the members don't know each other very well. The team is still in the storming stage because of the separation issues.
Which of the following should you consider?
Continually measuring and monitoring the actual cost versus the budget is done to _____.
The project manager has, as a prime responsibility, to assure proper integration of activities.
In which organizational form does the project manager probably have the easiest time in integrating work?
What is Project Portfolio Management?
Which tool is used to develop technical details within the project management plan?
Which of the following provides a comprehensive and consistent method of controlling the project and ensuring its success?
At the end of the project, what will be the value of SV?
Surveys have shown that the primary skill needed to be a project manager is communication skill. The typical project manager spends approximately ______ percent of his or her time communicating.
Which process includes facilitated workshops as a tool and technique?
Your management has decided that all orders will be treated as "projects" and that project managers will be used to update orders daily, to resolve issues, and to ensure that the customer formally accepts the product within 30 days of completion. Revenue from the individual orders can vary from US $100 to US $150,000. The project manager will not be required to perform planning or provide documentation other than daily status.
How would you define this situation?
All the techniques described below can be used to keep a meeting focused except:
You know that PV = 470, AC = 430, EV = 480, EAC = 500, and BAC = 525.
What is VAC?
Which of the following techniques uses historical information to estimate the activity duration?
A computer tape which contains historical project information is called ____ tape.