BCS ISEB-PM1 - BCS Foundation Certificate in IS Project Management
In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.
If project time and cost are not as important as the number of resources used each month, which of the following is the BEST thing to do?
The initial development of a Project Scope Management plan uses which technique?
Rolling wave planning is used as a tool and a technique in which of the following processes?
Which of the following is an input to the Direct and Manage Project Execution Process?
Inspection is a tool and technique for which of the following processes?
The procurement document is an input to which of the following processes?
How many knowledge areas are there according to PMBOK Guide?
The following reports are normally developed during the project closure phase?
Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?
During your project meeting, a problem was discussed, and a resolution to the problem was reached. During the meeting, the participants started wondering why they thought the problem was such a big issue. Sometime after the meeting, you received an email from one of the meeting participants saying they've changed their mind about the solution reached in the meeting and need to resurface the problem.
The solution reached during the initial project meeting is a result of which of the following conflict resolution techniques?
A team member notifies the project manager that the activities comprising a work package are no longer appropriate.
It would be BEST for the project manager to be in what part of the project management process?
You are in the middle of a major new facility construction project. The structural steel is in place and the heating conduits are going into place when a senior manager informs you that he is worried that the project will not meet the quality standards.
What should you do in this situation?
How is quality control performed?
You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements.
Which of the following is not a valid option?