Which ONE of the following options BEST describes a key characteristic of non-functional testing?

A.

Performing non-functional testing starting at the system test level.

B.

Conducting non-functional testing exclusively at the acceptance test level.

C.

Limiting non-functional testing to security testing and performance testing only.

D.

Ensuring non-functional testing focuses only on user experience and usability.

Which ONE of the following statements BEST applies to checklist-based testing?

A.

Checklists should contain general guidelines to ensure that all aspects of the software are covered.

B.

Checklists should contain specific test conditions that can be individually and directly checked.

C.

Checklists should primarily consist of automated test cases to maximize efficiency.

D.

Checklists should be used exclusively for functional testing, as they are unsuitable for non-functional testing.

Which of the following statements refers to good testing practice to be applied regardless of the chosen software development model?

A.

Tests should be written in executable format before the code is written and should act as executable specifications that drive coding

B.

Test levels should be defined such that the exit criteria of one level are part of the entry criteria for the next level

C.

Test objectives should be the same for all test levels, although the number of tests designed at various levels can vary significantly

D.

Involvement of testers in work product reviews should occur as early as possible to take advantage of the early testing principle

Which of the following is a test task that usually occurs during test implementation?

A.

Make sure the planned test environment is ready to be delivered

B.

Find, analyze, and remove the causes of the failures highlighted by the tests

C.

Archive the testware for use in future test projects

D.

Gather the metrics that are used to guide the test project

A test engineer finds a defect while testing. After the developer has fixed the defect, the test engineer decides to re-run a complete section of the tests. Which of the following is correct?

A.

The lest engineer should not re-run the tests, as they have already been run, and results recorded.

B.

The test engineer should not re-run the tests, they should be part of the developer tests.

C.

The test engineer should re-run the tests, in order to ensure that new defects have not been introduced by the fix.

D.

The test engineer should re-run the tests, because the defect shows that the test cases need to be updated.

For withdrawing money tram an Automated Teller Machine (ATM), the following conditions are required:

- The bank card is valid

- The PIN code is correct

- Money is available in the user's account

The following are some possible interactions between the user and the ATM:

- The entered card is invalid The card is rejected

- The PIN code is wrong The ATM asks for another PIN code

- The requested amount is more than available in the user's account: The ATM asks for another amount

- The requested amount is available in the user's account The ATM dispenses the money

Which test design technique should be used to cover all possible combinations of the in put conditions?

A.

Use case based testing

B.

Decision table

C.

Boundary value analysis

D.

Equivalence class partitioning

Consider a program that computes the factorial of a number (n). From the specifications you know that:

• I n < 0. a message "Value out of range" must be issued.

• If 0 < n < 100, the program calculates the factorial and returns the number

• If 100 < n < 200 message "Value out of range" must be issued

A.

There are 3 partitions - one for negative numbers, one for numbers up to 100 and the last one for numbers up to 200

B.

The equivalence partitions cannot be determined for this question because factorial of numbers close to 200 will be very large

C.

The equivalence partitions cannot be determined for this question because the error message for two partitions is exactly same

D.

The requirements are not correct because the partitions are overlapping

A system has valid input numbers ranging between 1000 and 99999 (both inclusive). Which of the following inputs are a result of designing tests for all valid equivalence classes and their boundaries?

A.

999.1000.23232.99999.100000

B.

999.1000.50000.100000.100001

C.

999.100000

D.

1000,50000,99999

Calculate the measurement error SD for the following estimates done using three point estimation technique-Most optimistic effort (a) -120 person days Most likely effort (m) -180 person days Most pessimistic effort (b) - 240 person days

A.

180

B.

120

C.

197

D.

20

Which of the following can be considered a VALID exit criterion?

I Estimates of defect density or reliability measures.

II. The completion and publication of an exhaustive Test Report.

III. Accuracy measures, such as code, functionality or risk coverage.

IV Residual risks such as lack of code coverage in certain areas.

A.

I, III, IV

B.

I, II, III

C.

III, IV

D.

II, III, IV