In what way do Configuration Management effects testing?

A.

Without proper configuration management, test planning cannot proceed.

B.

Proper configuration management ensures that testers can uniquely identity the tested item

C.

Configuration management is important for developers, not for testers

D.

There is very little influence of configuration management practices on the test project.

A possible risk of introducing test automation is:

A.

the tool may not be fit-for-purpose.

B.

the tool may create additional development dependencies.

C.

the tool may not be compatible with the development platform.

D.

the tool will be owned and maintained by developers and replace testers.

A test engineer finds a defect while testing. After the developer has fixed the defect, the test engineer decides to re-run a complete section of the tests. Which of the following is correct?

A.

The lest engineer should not re-run the tests, as they have already been run, and results recorded.

B.

The test engineer should not re-run the tests, they should be part of the developer tests.

C.

The test engineer should re-run the tests, in order to ensure that new defects have not been introduced by the fix.

D.

The test engineer should re-run the tests, because the defect shows that the test cases need to be updated.

Which ONE of the following is a GOOD testing practice that is INDEPENDENT of the chosen SDLC (Software Development Life Cycle) model?

A.

Testers are involved in reviewing work products as soon as the final version of this documentation is available so that this earlier testing and defect detection can support the “shift-left" strategy.

B.

Test analysis and design for a specific test level begin during the corresponding development phase of the SDLC, allowing testing to follow the principle of late testing.

C.

For every software development activity, there is a corresponding testing activity, ensuring that all development activities are subject to quality assurance.

D.

Different test levels have specific and overlapping test objectives, allowing tests to be appropriate to specific test object types while managing redundancy.

A state transition diagram describes a control system’s behavior in different operational modes. The initial state is “NORMAL MODE”.

Which ONE of the following test cases covers an INVALID sequence?

A.

NORMAL MODE → DIAGNOSTIC MODE → DEGRADED MODE → EMERGENCY MODE → DIAGNOSTIC MODE → NORMAL MODE → DIAGNOSTIC MODE

B.

NORMAL MODE → DEGRADED MODE → NORMAL MODE → DIAGNOSTIC MODE → DEGRADED MODE → EMERGENCY MODE → DIAGNOSTIC MODE

C.

NORMAL MODE → DIAGNOSTIC MODE → DEGRADED MODE → EMERGENCY MODE → DIAGNOSTIC MODE → NORMAL MODE → DEGRADED MODE

D.

NORMAL MODE → DIAGNOSTIC MODE → NORMAL MODE → DIAGNOSTIC MODE → EMERGENCY MODE → DIAGNOSTIC MODE → NORMAL MODE

Which of the following would be the LEAST likely to be used as the basis for a test exit criteria?

A.

Test schedules

B.

Cost of testing performed so far

C.

Confidence of testers in tested code

D.

Number of unfixed defects

Which of the following statements about white-box testing is FALSE?

A.

Static testing can benefit from using code-related white-box test techniques during code reviews.

B.

White-box testing allows suggesting test cases for increasing coverage levels which are based on objective measures

C.

Achieving full code coverage for a component or a system ensures that it has been fully tested

D.

Black-box testing can benefit from using code-related white-box test techniques to increase confidence in the code.

A software calculates the annual car tax using three inputs:

- E; the emission level of the vehicle

- P: the power of the vehicle

-T the type of the vehicle

The input value for P can be integer positive values between 15 and 350.

Which of the following answers contains a correct list of a boundary values for the P input?

A.

14,351

B.

14,15,350,351

C.

15,350

D.

5.175.500

Given the following requirement:

Requirement ID: 2 8

Requirement Description Additional Entrance Fee

Detailed Description

An additional fee of S3 is charged during the weekend, but

1) Visitors aged under 7 are not charged.

2) Visitors aged 7 to 13 inclusive get a 20% discount off the additional fee.

3) Visitors aged greater than 65 get a 50% discount off the additional fee.

Age should be an integer of 0 or above.

Weekend means Friday to Sunday inclusive.

Which of the following statements is NOT correct?

A.

Thursday is a valid input boundary value.

B.

A minimum of 6 valid test cases are derived from boundary value analysis based on input age.

C.

$3.01 is a valid output boundary value.

D.

7 and 13 are boundary values for the equivalence partition including age 10.

After being in operation for many years, a document management system must be decommissioned as it has reached its end of life. This system will not be replaced by any other new system. A legal obligation provides that all documents within the system must be kept for at least 20 years in a state archive. Which of the following statements about maintenance testing for decommissioning of this system is TRUE?

A.

No maintenance testing is required as this system will not be replaced.

B.

Data migration testing is required as part of maintenance testing

C.

Confirmation testing is required as part of maintenance testing.

D.

Regression testing is required as part of maintenance testing