Refer to Exhibit:

A Foundation install must be done on four NX nodes for a new customer. A consultant need to set up the network onsite before imaging the nodes through the Foundation tool.
The nodes are equipped with two SFP28 25GbE NICs with dual ports, and a 10GBase-T NIC with dual ports as well The customer’s ToR switches are 25GbE datacenter switches, already in production.
What is the appropriate hardware to perform the most reliable imaging of these NX nodes?
An administrator protected a DB VM running on a Nutanix cluster with NearSync Replication, which schedules to repeat every 15 minutes â–¡ to a second site. The daily change rate is low. During nightly backups, the replication window is missed due to write volume.
Which two options describe the expected behavior? (Choose two.)
A consultant discovers that while the Foundation VM and the consultant's laptop are able to ping each other nodes are rea discovered while trying to run Foundation on the customer's network.
What should the consultant do to resolve the issue?
An administrator is migrating 5MB shares from a third-party platform to Nutanix Files with the following characteristics:
• Shares contain user profile directories
• DFS-N will be used
How should the administrator create target shares for this migration?
A customer asks where to find the passwords used for initial cluster configurations.
Which document contains the requested information?
An administrator is deploying several new application VMs to a Nutanix cluster. The application is very transactional with a 28/72 random, read/write ratio.
What should the administrator do?
For several days, an administrator notices the following alerts:
• CVM NIC Speed Low Warning Alerts
• Warning Alerts of CVM NIC not performing at optimal speed
• CVM is disconnected from the network Critical Alert
• Network Visualization page shows excessive dropped packets on CVM/Host
Which steps should be taken to determine which problem should be addressed first?
The networking team makes changes to the Top of Rack switches to which the Nutanix cluster are attached. A few VMs are able to communicate with each other on the same node but are unable to connect to other parts of the network.
What is the likely cause of this issue?
Which container advanced setting should be configured to prevent ISO container images from exceeding a 100GB limit.
An administrator needs to forecast infrastructure requirements for a new program and its associated applications. Prior to the projected start of the new program, all existing applications will be decommissioned.
How should the administrator perform this task?