A consultant has configured the cluster networking via the Prism Element Web Console but noticed an error message indicating a bond mode mismatch between an AHV host and the virtual switch (vSwitch0).

Which two commands should the consultant use to manually change the bond mode to active-active? (Choose two.)

A.

manage_cvs --bridge br0 --interfaces eth0,eth2 --bond_name br0-up --bond_mode balance-slb update_uplinks

B.

ovs-vsctl set port br0 tag=0

C.

acli net.disable virtual switch vSwitch0

D.

manage_cvs --bridge br0 --interfaces eth0,eth2 --bond_name br0-up --bond_mode balance-tcp --lacp_mode fast --lacp_fallback true update_uplinks

A consultant is reviewing a customers Pre-delivery Questionnaire.

The customer wants to deploy their cluster with ESXi as the hypervisor with vSphere Distributed Switch. The customer will be using Cisco Nexus 9k as their switch choice In the kick-off call, it is confirmed that the customer has a business requirement to use LACP in their environment.

What should the consultant ensure that the customer configures on the port-channel interface before deployment?

A.

show pore-channel

B.

no lacp graceful-convergence

C.

service unsupported-transceiver

D.

no lacp suspend-individual

An administrator is performing a set of routine checks and notes that Prism Central is running with 4 vCPUs and 21 GB RAM. The organizations environment is based on two Nutanix clusters with 170 VMs plus a Legacy vSphere infrastructure. No manual changes have been done on Prism Central VM.

Which configuration justifies the current Prism Central configuration?

A.

Nutanix Move is running on Prism Central to import VMs from the Legacy Cluster.

B.

Prism Central was installed for Large Deployment environments.

C.

Prism Central is running on the legacy duster and requires more RAM.

D.

Nutanix Leap and Nutanix Flow have been enabled on Prism Central

A consultant creates a Nutanix cluster using the 10.10.10.0/24 network and VLAN 10. The customer creates a VM network inside the Prism using VLAN 20. The customer starts to create VMs but is unable to ping the default gateway from these new systems.

What is causing the issue?

A.

The CVM/hypervisor must be on an untagged VLAN.

B.

The switch port is not set up as a trunk.

C.

Only one VLAN is supported on AHV.

D.

The CVM/hypervisor cannot use the same VLAN as guest VMs.

The consultant is deploying a 20-node AHV cluster, as part of a Nutanix Files deployment.

How many FSVMs can the consultant deploy in this environment?

A.

16

B.

18

C.

20

D.

22

Refer to the exhibit.

A consultant is installing AOS 5.10 and ESXi 6.5 on three nodes. During the Foundation process, ESXi 6.5 is not available as one of the choices for hypervisor.

Which solution should the consultant use?

A.

Upload ESXi image to /home/Nutanix/foundation/nos/hypervisor/esx.

B.

Restart Foundation VM and refresh Foundation page.

C.

Update the Foundation whitelist from the support portal.

D.

Upload ESXi image to /home/Nutanix/foundation/isos/hypervisor/esx.

An administrator is responsible for the following Nutanix Enterprise Cloud environment:

• A central datacenter with a 20-node cluster with 1.5PB of storage

• Five remote sites each with a 4-node cluster with 200TB storage

The remote sites are connected to the datacenter via 1GB links with an average latency of 6 ms RTT. What is the minimum RPO the administrator can achieve for this environment?

A.

0 minutes

B.

15 minutes

C.

1 hour

D.

6 hours

A consultant is deploying a two-node cluster at a remote branch office.

Which component must be available to complete cluster configuration?

A.

Prism Central

B.

Witness VM

C.

Remote Site

D.

Protection Domain

A consultant runs the Foundation Applet and discovers all the nodes. The consultant wants to use the latest version of Foundation for imaging for support purposes and to cover the latest hardware and software hypervisor support.

What should the consultant do to upgrade Foundation on a node?

A.

Use crash cart and manually upgrade Foundation files on one node.

B.

Use latest version of Foundation to reimage all the nodes.

C.

Use the Foundation VM to upgrade Foundation on all nodes.

D.

Use the Foundation Applet to upgrade Foundation on a single node.

During the cluster deployment, a consultant conducts operational tests on a vCenter-managed ESXi hypervisor.

As a part of tests, vCenter must place the host into maintenance mode, however, the task is stuck and the CVM is not shutting down automatically.

What should the consultant do to resolve the issue?

A.

Shutdown the CVM using cvn_shutdown -P now.

B.

Put the node into maintenance mode using

C.

acli host.enter_maintenance_mode Hypervisor address.

D.

Put the node into maintenance mode using ’-/serviceability/bin/esx-shutdown

-s cwn_.£p_addr

E.

Shutdown the CVM using shutdown -h now.