A consultant completes a manual cluster creation of AHV. When the consultant logs into Prism Element, critical error messages appear regarding the hypervisor and NTP.

What component or setting, if misconfigured, would cause these errors?

A.

Cluster name

B.

Name Server

C.

Cluster Virtual IP

D.

Data Services IP

A consultant is working on an expansion project for a customer that has an existing 7-node RF2 cluster. The customer has purchased four more nodes to add to the cluster. All of the hardware is identical between the existing hardware and newly purchased hardware.

Currently, the 7-node cluster has the following utilization:

•CPU: 48%

•Memory: 66%

•Storage: 91%

During the kick-off call, the customer mentioned they'd like to reserve storage capacity on the cluster if a node were to fail in the future.

What's the safest and best way to implement this on the cluster?

A.

Expand the cluster with the additional nodes and enable Reserve Rebuild Capacity.

B.

Enable Reserve Rebuild Capacity and expand the cluster with the additional nodes.

C.

Expand the cluster with the additional nodes and enable HA reservation.

D.

Enable HA reservation and expand the cluster with the additional nodes.

Refer to the exhibit.

A system administrator is using Range-Autofill tool to assign IP addresses to setup a multi-block cluster based on the following configuration:

Which additional changes must be made during the Foundation process to configure the cluster correctly?

A.

Change host names

B.

Reorder block serial

C.

Change IP address

D.

Reorder blocks

A consultant is deploying a Nutanix cluster at a customer location. The consultant will be deploying the latest AOS along with the latest Nutanix hardware.

Which three references should the consultant review prior to this installation? (Choose three.)

A.

Release Notes

B.

Software Product Interoperability

C.

Field & Security Advisories

D.

End-Of-Life (EOL) Information

E.

Acropolis Advanced Administration Guide

A customer wants to expand an existing cluster with three additional nodes. After running the Foundation process on the new nodes, the customer realizes that the wrong IPs where used and the nodes are configured on a different network. The customer decides to create a new cluster instead.

Which method should be used to recreate the cluster?

A.

Log into IPMI and use cluster create command to create the cluster.

B.

Log into CVM and use cluster create command to create the cluster.

C.

Log into Hypervisor and use cluster create command to create the cluster.

D.

Foundation all nodes again and create the cluster.

A consultant is working to setup the network before starting the Foundation process.

How should the consultant complete this task?

A.

Using the shared IPMI port, ensure that the connected switch can auto-negotiate to 1 Gbps.

B.

Disable IPv6 on the network to which the nodes are connected to ensure that IPv6 unicast is blocked.

C.

Ensure the IPMI of the nodes are reachable using pre-configured IPMI IPv6 addresses.

D.

On Nutanix NX Series, connect the IPMI port and any one of the data ports to the switch.

A consultant is preparing for a cluster deployment and evaluates portable Foundation.

Laptop configuration is as follows:

•CPU: 2.8 GHz Quad-Core Intel Core i7

•Memory: 4GB RAM

During the installation, the consultant encounters some errors and tries to troubleshoot.

What could prevent successful installation and Foundation usage?

A.

Gatekeeper must be enabled

B.

Oracle VirtualBox is installed on the laptop

C.

Laptop configuration does not meet installation requirements

D.

Firewall Stealth Mode is disabled

An administrator inherits a new Nutanix environment and logs in to a CVM to check the network configuration. The configuration is as follows:

Which action should the administrator take to improve network performance?

A.

Configure VLAN tagging both on br0 and br1 and their physical interfaces.

B.

Add eth0 and eth1 to the br0-up bond

C.

Configure balance-sib or balance-tcp mode for br0-up if switch configuration allows

D.

Remove one 10 Gbs interface from br0-up to make sure all 10 Gbs can be used.

A consultant configures an ESXi cluster which will utilize a vSphere Distributed Switch (vDS). The consultant has just migrated the first host to the dvSwitch when several alerts appear within Prism Element regarding Host-to-CVM connectivity.

What is causing these alerts?

A.

The consultant migrated the CVM Backplane and VM network adapter over to the vDS.

B.

The consultant migrated the CVM svm-iscsi-pg network adapter over to the vDS.

C.

The consultant migrated the CVM Backplane network adapter over to the vDS.

D.

VLAN tags are incorrectly configured on the vDS port groups.

Refer to the exhibit.

An administrator notices a critical alert on the Metro Availability Protection Domain What is causing this alert?

A.

Metro Availability Protection domain is active on the remote site.

B.

VMware Site Recovery Manager is handling a failover event

C.

Metro Availability did not fail over and caused an outage.

D.

vSphere moved VMs to the remote container, and the VMs must be moved back.