Which ADM Phase includes initial implementation planning?

A.

Phase H

B.

Phase E

C.

Phase A

D.

Preliminary

What is an objective of the ADM Implementation Governance Phase?

A.

To provide continual monitoring of the governance framework

B.

To ensure conformance for the target architecture

C.

To finalize the Implementation and Migration Plan

D.

To establish the resources for architecture governance

Which of the following best describes the purpose of the Architecture Requirements Specification?

A.

It contains an assessment of the current architecture requirements

B.

It provides a set of statements that outline what a project must do to comply with the architecture

C.

It is sent from the sponsor and triggers the start of an architecture development cycle

D.

It defines the scope and approach to complete an architecture project

Consider the illustration of an architecture development cycle.

Select the correct phase names corresponding to the labels 1, 2 and 3?

A.

1 Continuous Improvement - 2 Migration Planning - 3 Architecture Vision

B.

1 Requirements Management - 2 Implementation Governance - 3 Preliminary

C.

1 Requirements Management - 2 Change Management - 3 Strategy

D.

1 Architecture Governance - 2 Implementation Governance - 3 Preliminary

What is used to structure architectural information in an orderly way so that it can be processed to meet stakeholder needs?

A.

A Stakeholder Map

B.

An Architecture Framework

C.

Content Metamodel

D.

An EA Library

Which of the following is a purpose of Phase A of the TOGAF ADM?

A.

Identifying key stakeholders

B.

Defining the Enterprise strategy

C.

Describing the target architecture

D.

Developing an Enterprise Architecture Capability

Complete the following sentence.

________ provide context for architecture work, by describing the needs and ways of working employed by the enterprise.

A.

Architecture Contracts

B.

Stakeholder needs

C.

Strategy and vision

D.

Business principles, business goals, and business drivers

Complete the sentence Business Transformation Readiness Assessment is_________________.

A.

a joint effort between corporate staff lines of business and IT planners

B.

to ensure the active support of powerful stakeholders

C.

a way to put building blocks into context thereby supporting re-usable solutions

D.

widely used to validate an architecture that is being developed

Which of the following describes the practice by which the enterprise architecture is managed and controlled at an enterprise-wide level?

A.

Corporate governance

B.

Architecture governance

C.

IT governance

D.

Technology governance

In the ADM, what is the name for documents that are not finished and not approved?

A.

interim

B.

draft

C.

version 0.1

D.

incomplete