You are a Product Owner. The Developers are close to the end of a Sprint and ask you for 3 extra days to complete their work. They feel that if they do not get the extra time, they might look bad in front of stakeholders, who are already skeptical of using an agile approach. What should you do? (choose the best answer)

A.

Cut back on testing, or leave some items incomplete, so long as the Developers can "substantially meet" their goal.

B.

Agree to extend the Sprint but ask the team to be more realistic when they plan Sprints in the future.

C.

Ask the Developers to work longer hours to meet their goal.

D.

Ask the Developers to commit to what was agreed and find a solution for the problem.

E.

Do not extend the Sprint and stick to the original timebox. Work with the stakeholders to explain why transparency and openness are important.

Which of the following is NOT a good reason to keep a team together for an extended period oftime? (choose the best answer)

A.

To improve a team’s focus.

B.

To improve the exchange of expertise within the Scrum Team.

C.

To improve team collaboration.

D.

To improve utilization.