Which of the following is a quality assurance tool?

A.

Defining project goals

B.

Identifying the root cause analysis

C.

Assessing employee efficiency

D.

Assessing skill gaps

During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.

INSTRUCTIONS

Review the email with the latest updates sent by the project sponsor and respond in

the following order:

1. Select the best tool for tracking the server migration progress.

2. Select the new critical path.

3. Select the correct number of engineers required for the server migration phase.

If at any time you would like to bring back the initial state of the simulation, please click

the Reset All button.

Select the Appropriate Tool:

Select the new critical path.

Option A

Option B

Option C

Which of the following is the best example of CapEx?

A.

Taxes

B.

Vehicles

C.

Salaries

D.

Utilities

A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?

A.

Cultural differences

B.

Technological factors

C.

Time zones

D.

Language barriers

Which of the following is a consideration when determining a project's ESG factors?

A.

Project management methodology

B.

IT infrastructure security

C.

Proper accounting practices

D.

Corporate values compliance

A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?

A.

Create a list of tasks and share it with the team.

B.

Resend the scope of work to the team.

C.

Review the Gantt chart weekly with the team.

D.

Have the project sponsor meet with the team.

A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

A.

Creation of a social news forum

B.

Management directives to use the new system

C.

New user kickoff meeting

D.

Monthly feedback and training sessions

While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue. Which of the following should the project manager and contractor review?

A.

Scope of work

B.

Request for proposal

C.

Vendor rules of engagement

D.

Project schedule

A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?

A.

Collate the lessons learned.

B.

Perform a gap analysis.

C.

Review existing artifacts.

D.

Conduct a retrospective.

An existing application that is highly utilized by clients is moving to a new release. Which of the following environments contains this application?

A.

Development

B.

Production

C.

Testing

D.

QA