CompTIA PK0-005 - CompTIA Project+ Certification (2025)
A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?
During an active project, the finished product is not meeting quality specifications Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?
The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project’s level of compliance with the budget. Which of the following best describes what the project manager should do to assist the client?
Which of the following pieces of data are examples of Pll?
A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?
A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?
A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?
A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?
Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?
A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?