Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

CompTIA PK0-005 - CompTIA Project+ Certification (2026)

Page: 10 / 14
Total 447 questions

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

A.

Time and materials contract

B.

Master service agreement

C.

Fixed-price contract

D.

Statement of work

E.

Cost-plus agreement

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

A.

Determine budget constraints.

B.

Validate the business case.

C.

Update the project charter.

D.

Create a project schedule

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?

A.

Exploit the risk.

B.

Accept the risk.

C.

Avoid the risk.

D.

Transfer the risk.

A project manager is managing a virtual team across the country. As reported in the retrospective, the team morale has decreased due to additional production issues. Which of the following meeting tools is the best option to record results in the retrospective?

A.

Presentation

B.

Wiki

C.

Chat

D.

Polling

A PM is working on the schedule for a project that has technical tasks and requires a SME's knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

A.

Gantt chart

B.

Project organization chart

C.

Program Evaluation Review Technique chart

D.

Milestone chart

Two stakeholders, who have a history of animosity toward one another, are in disagreement during a project. The project's timeline depends on the stakeholders accomplishing their tasks. Which of the following conflict resolution methods would be best to utilize?

A.

Smoothing

B.

Confronting

C.

Forcing

D.

Compromising

Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?

A.

Smoke testing

B.

Regression testing

C.

Unit testing

D.

User acceptance testing

A project manager decided to host the development environment on a cloud service. Which of the following would the project manager most likely use for this purpose?

A.

IaaS

B.

XaaS

C.

DaaS

D.

SaaS

During the execution phase of a project, the project team faced an unexpected website downtime The project manager how a brainstorming session and the team identified causes and effects tor the problem Now the project team needs to analyze and determine whether the particular cause and effect are related by using one of the following charts. Which of the following should the team use?

A)

B)

C)

D)

A.

Option A

B.

Option B

C.

Option C

D.

Option D

A project manager submits a change request. The change request is rejected because of code freeze. Which of the following actions should the project manager take next?

A.

Update the risk register.

B.

Escalate the issue for exceptional approval.

C.

Communicate to the stakeholders.

D.

Submit a duplicate change request.