Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

CompTIA PK0-005 - CompTIA Project+ Certification (2026)

Page: 10 / 14
Total 460 questions

The quarterly financial report displays losses from a project even though the project was completed successfully several weeks ago. Which of the following actions should the project manager perform next?

A.

Remove access.

B.

Complete the project sign-off.

C.

Release the resources.

D.

Outline the lessons learned.

As part of a global project, the project manager wants to ensure there is no disruption in the day-to-day performance among project team members around the world Which of the following should the project manager consider doing as part of the project planning?

A.

Monitoring the project team

B.

Creating a handoff process

C.

Colocating the project team

D.

Creating a separate statement of work

Which of the following best describes a benefit of the CI/CD process?

A.

Software delivery is sped up without compromising quality

B.

Incremental changes are done at the end of the project

C.

The software is integrated with other projects easily

D.

Updates are released every sprint

Which of the following can be inferred?

A.

The project will be completed on time.

B.

Task D must be reworked.

C.

Task B needs to be finished before task C starts.

D.

The project is over budget and behind schedule.

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the

following has the project manager identified?

A.

Technological factors

B.

Poor sample data

C.

Language barriers

D.

Scope creep

A project team member recalls a specific chat with another member that contained key information related to a previous project, which no one else on the project team is aware of. Which of the following best describes what was needed to address this concern?

A.

Integrity

B.

Security

C.

Archival

D.

Lessons learned

Which of the following is a characteristic that defines a project?

A.

Will produce a profit

B.

Uses outside resources

C.

Requires a well-defined scope

D.

Has a defined start and finish

During a phase review, two stakeholders discuss the approval of a deliverable. The project manager convinces the stakeholders to agree on a common solution. Which of the following best describes what the project manager did to gain approval from both stakeholders?

A.

Force

B.

Smooth

C.

Compromise

D.

Avoid

A project manager requests the testing team to figure out if a website allows multiple users to be signed in at the same time. Which of the following testing methods would be best for the testing team to use?

A.

Regression

B.

Unit

C.

Stress

D.

Smoke

A retail store is rolling out a new point-of-sale solution to several locations where the staff members normally use cash registers. Which of the following activities will best assist staff members with integrating this new solution? (Select two).

A.

Documentation

B.

Team collaboration

C.

Gap analysis

D.

Training sessions

E.

Touch points

F.

Progress monitoring