Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

CompTIA PK0-005 - CompTIA Project+ Certification (2025)

Page: 10 / 11
Total 362 questions

A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?

A.

Consult with the legal department.

B.

Update the issue log.

C.

Start a new RFP immediately.

D.

Perform a PERT analysis.

During an active project, the finished product is not meeting quality specifications Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?

A.

Communicate the change status.

B.

Document change recommendations

C.

Create a change request.

D.

Implement the changes

The client asks the project manager to establish a communication channel. The client wants to understand what is needed from them and to know the project’s level of compliance with the budget. Which of the following best describes what the project manager should do to assist the client?

A.

Grant the client access to the project repository.

B.

Create a chat to communicate in real time.

C.

Schedule a weekly status meeting.

D.

Send a weekly status report by email.

Which of the following pieces of data are examples of Pll?

A.

Medical record and test result values

B.

IP address and email address

C.

Name and year of birth

D.

X-ray and blood type

A team is analyzing the backlog in order to decide what to include in the next sprint. Which of the following aspects is the most important for the team to take into consideration?

A.

Time to be fixed

B.

Impact to project

C.

Issue category

D.

Resource availability

A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

A.

Issue log

B.

Gantt chart

C.

Milestone chart

D.

Change control log

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

A.

Scope creep

B.

Collecting requirements

C.

Decision-making

D.

Project change

A project manager provided the team with a summary Gantt chart for the project. The team, however, has expressed interest in seeing the sequencing between all of the tasks. Which of the following should the project manager provide?

A.

Project network diagram

B.

Fishbone diagram

C.

Burndown chart

D.

Milestone chart

Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

A.

Maintenance window

B.

Risk assessment

C.

Operational security

D.

Validation check

A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

A.

Status report

B.

Project plan

C.

Change log

D.

Meeting minutes