CompTIA PK0-005 - CompTIA Project+ Certification (2026)

Page: 12 / 14
Total 447 questions

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?

A.

RFB

B.

RFQ

C.

RF

D.

RFP

A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?

A.

ROI

B.

KPI

C.

RACI

D.

SOW

Which of the following should be considered first when determining the privacy management for project data?

A.

Evaluating the current privacy protection program

B.

Understanding applicable privacy regulations

C.

Maintaining awareness of industry best practices

D.

Implementing security role-based controls

A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?

A.

List both positively and negatively impacted stakeholders.

B.

Update the communication plan with the new findings.

C.

List the negatively impacted stakeholders only.

D.

List the positively impacted stakeholders only.

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

A.

Remove the team member's access.

B.

Release the project resources.

C.

Collect the stakeholders' feedback.

D.

Have the closeout report approved.

During project initiation, a project manager needs to identify goals and deliverables that should be completed by the end of the project and also meet certain cost and time factors. Which of the following would best align with these needs?

A.

Work breakdown structure

B.

Change log

C.

Project success criteria

D.

Milestone chart

A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

A.

Responsibility assignment matrix

B.

Acceptable communication channels

C.

Risk registry

D.

Staff directory

A web designer is currently verifying that the website data is compliant. Which of the following data types will be protected after confirming that the controls are in place?

A.

Credit cards

B.

Mission statements

C.

Site certificates

D.

Trademarks

Which of the following activities are performed during the closing phase? (Select three).

A.

Requesting project charter sign-off

B.

Recognizing project team efforts and rewarding team members

C.

Working with the financial team to obtain return of investment

D.

Revoking resource credentials from the system

E.

Updating the risk register with new findings

F.

Informing the functional manager about the release of resources

G.

Monitoring project team performance

A project manager is responsible for implementing a large, centralized repository that stores raw information from various sources in a structured and organized way. Which of the following should the project manager implement?

A.

Shared folder

B.

Infrastructure

C.

Multitiered architecture

D.

Data warehouse