CompTIA PK0-005 - CompTIA Project+ Certification (2026)

Page: 13 / 14
Total 460 questions

A project manager makes a list of the smallest activity components in the project. Which of the following is the project manager building?

A.

Milestone chart

B.

Task board

C.

Work breakdown structure

D.

Detailed project plan

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

Which of the following issues should be addressed FIRST?

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.

A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?

A.

Identify project risks and plans to address them.

B.

Identify business needs and product descriptions.

C.

Create a work breakdown structure for the project.

D.

Create a work schedule for the project team to follow.

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

A.

ROI.

B.

SOW.

C.

RFI.

D.

RPR

Which of the following metrics BE ST measures the alignment of the information security program to operational objectives?

A.

Percentage of controls with identified business owners

B.

Percentage of risk investments with defined business cases

C.

Ratio of control cost to operational budget

D.

Senior management satisfaction scores related to the security program

Which of the following best describes a program in the context of project management?

A.

It is a group of unrelated projects within an organization

B.

It is used to represent the daily activities of multiple projects

C.

It is a consolidation of related projects with a common goal

D.

It provides the definition of a project workload

During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?

A.

Work breakdown structure

B.

Project charter

C.

Quality plan

D.

Solution design

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).

A.

Risk report

B.

Defect log

C.

Issue log

D.

Backlog

E.

Change log

F.

Progress report

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM ' s time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

A.

Perform a root cause analysis.

B.

Organize a stakeholder meeting

C.

Escalate the issue to the CCB

D.

Contact the PMO for assistance.

A project manager and team are reviewing a task that is supposed to take 9 days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional 5 days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

13 days and $3,600