CompTIA PK0-005 - CompTIA Project+ Certification (2026)
A project manager makes a list of the smallest activity components in the project. Which of the following is the project manager building?
A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

Which of the following issues should be addressed FIRST?
A project manager is starting a new project for an international supplier. Which of the following is the first step the project manager should take to initiate the project?
A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:
Which of the following metrics BE ST measures the alignment of the information security program to operational objectives?
Which of the following best describes a program in the context of project management?
During a project closure meeting, stakeholders did not agree that the project achieved the expected results. Which of the following documents should the project manager consult?
A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Select TWO).
While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM ' s time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?
A project manager and team are reviewing a task that is supposed to take 9 days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional 5 days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?
