During the execution phase, user accepted testing failed; nonetheless, the vendor PM is insisting that the program manager approve the invoice for this phase. Which of the following actions should the Program manager take?

A.

Escalate the issue with the project sponsor and ask for assistance in managing the situation.

B.

Work with the vendor to achieve a compromise that benefits everyone.

C.

Approve the invoice to avoid damaging the relationship with the vendor.

D.

Schedule a call with the vendor PM and vendor executive to review the statement of work.

A new stakeholder has joined a project and has a different vision of the scope. The sponsor is requiring the project manager to provide a document in which the initial scope of the project is defined. Which of the following should the project manager do next to clarify the differences?

A.

Create a new project management plan.

B.

Collect all project meeting minutes.

C.

Perform project scope management.

D.

Review the project charter.

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project ' s production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?

A.

Finish-to-start

B.

Start-to-start

C.

Finish-to-finish

D.

Start-to-finish

A PM is working on the schedule for a project that has technical tasks and requires a SME ' s knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates. Which of the following is the best tool to track this data?

A.

Gantt chart

B.

Project organization chart

C.

Program Evaluation Review Technique chart

D.

Milestone chart

Project team members are leaving the company due to a stressful work environment. The project manager needs to capture this concern about potentially losing team members again. Which of the following logs should the project manager use?

A.

Risk

B.

Change

C.

Defect

D.

Issue

Which of the following is an intended outcome of a stand-up meeting?

A.

To identify team members for next tasks

B.

To identify future tasks

C.

To identify stakeholders for next tasks

D.

To identify blocking tasks

A project team is reviewing the project plan and related documents and identifies tasks that could be spread into smaller deliverables. Which of the following documents should the team edit first?

A.

Risk assessment

B.

Preliminary scope statement

C.

Work breakdown structure

D.

Milestone chart

A company purchases new software. The project manager needs to present the new software’s features to the stakeholders. Which of the following meeting types should the project manager and stakeholders have?

A.

Status

B.

Focus

C.

Brainstorming

D.

Informative