Which of the following provides the best justification for undertaking a project?

A.

Scope statement

B.

Business case

C.

Sponsor request

D.

Project charter

A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:

• Two developers

• High uncertainty about existing systems

• Risk of frequent requirement changes

• Tight deadlines

Which of the following project methodologies would be best to use in this situation?

A.

PRINCE2

B.

Scrum

C.

SAFe

D.

XP

Which of the to and allowing interactive feedback from a project team?

A.

Text message

B.

Chat

C.

Email

D.

Videoconference

Which of the following activities would force a team to remove a new package and leave the previous one during a smoke test?

A.

Rollback plan

B.

Downtime stage

C.

Maintenance window

D.

Validation checks

A software engineer notices that the newest update to the reporting software includes many new features that were not defined in the requirements document. Which of the following steps should the engineer take next?

A.

Seek approval before continuing

B.

Edit the requirements document

C.

Disregard the update

D.

Notify the users of the new features

Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?

A.

Variable costs

B.

Fixed costs

C.

Front-loaded

D.

Time and materials

The project manager sends individual messages to team members about what must be accomplished. However, the team communicates confusion about the tasks assigned. Which of the following communication methods would be best to use?

A.

Informal internal

B.

Asynchronous verbal

C.

Synchronous external

D.

Formal written

Which of the following best describes a manufacturer's obligation to repair or change, without extra costs, any part of a product that is not functioning?

A.

Service-level agreement

B.

Functional testing

C.

Warranty period

D.

Audit

As a result of an internal assessment, the steering committee states that the company does not currently have the required skill set or technical tools to develop a particular feature in the project. Which of the following procurement methods would help the company?

A.

Subscription

B.

Subcontract

C.

Lease

D.

Build

A project sponsor is trying to use the ROI to determine if the project should be approved. Which of the following best describes what the project sponsor needs?

A.

An analysis of the current situation and the desired outcome

B.

A document with the description of project deliverables and vendor's responsibilities

C.

A description of the value that the project will bring to the company after the investment

D.

An analysis of the costs related to normal operations of the company