During the execution phase, user accepted testing failed; nonetheless, the vendor PM is insisting that the program manager approve the invoice for this phase. Which of the following actions should the Program manager take?

A.

Escalate the issue with the project sponsor and ask for assistance in managing the situation.

B.

Work with the vendor to achieve a compromise that benefits everyone.

C.

Approve the invoice to avoid damaging the relationship with the vendor.

D.

Schedule a call with the vendor PM and vendor executive to review the statement of work.

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

A.

ROI.

B.

SOW.

C.

RFI.

D.

RPR

Which of the following best describes a program in the context of project management?

A.

It is a group of unrelated projects within an organization.

B.

It is used to represent the daily activities of multiple projects.

C.

It is a consolidation of related projects with a common goal.

D.

It provides the definition of a project workload.

Which of the following considers factors such as reliability, scalability, security, and cost-effectiveness within project goals and objectives?

A.

DevOps architecture

B.

Computing services

C.

Data warehouse

D.

Networking and connectivity

A team found a deficiency in an application and is proposing improvements, but the sponsor requests a business case. Which of the following best describes the intended objective of the business case?

A.

To identify the potential risk and issues for the project

B.

To determine the timeline and budget of the project

C.

To define the specific tasks required to create the project

D.

To specify what problem is being solved by the project

A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

14 days and $4,000

While developing a project charter, a PM discovers that some of the legal requirements have not been addressed during the project concept preparation, which could result in significant financial penalties against the organization. The PM knows that implementation of appropriate changes is costly and will exceed the budget and scope of the project. Which of the following should the PM do FIRST?

A.

Escalate the finding to the change control board.

B.

Add a risk to the risk register for validation.

C.

Consult the RACI matrix to identify ownership of the risk.

D.

Have a meeting with the project sponsor and main stakeholders.

A project team is working on a document to precisely describe the success criteria that should be fulfilled by a product. Which of the following documents is the team preparing?

A.

Project scope

B.

Quality plan

C.

Contract obligations

D.

Work breakdown structure

A sponsor prefers to communicate with the team using email, phone calls, conversations in the hallway, and impromptu meetings. Which of the following types of communication is the sponsor using?

A.

Informal communication

B.

Formal communication

C.

Synchronous communication

D.

Asynchronous communication

During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?

A.

Business requirement

B.

Client statement of work

C.

Formal contract

D.

Project charter