CompTIA PK0-005 - CompTIA Project+ Certification (2025)
During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?
A project manager provided details regarding the completion of the following tasks:
Vendor selection took less time than planned.
Equipment procurement took less time than estimated.
Equipment installation went according to schedule.
Which of the following should the project manager update?
A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication. The project manager should update the stakeholder register with:
As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?
Which of the following activities should a project manager perform during the closing phase? (Select three).
A project manager and team are currently in the planning phase of a project. Which of the following should the team do during this phase?
Which of the following is a quality assurance tool?
A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?
Halfway through a project, the sponsor states that the project is taking too long to complete. Which of the following should the project manager consult?
A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?