Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

CompTIA PK0-005 - CompTIA Project+ Certification (2026)

Page: 5 / 14
Total 447 questions

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

A.

RFI

B.

RACI

C.

WBS

D.

SOW

A company is starting a new implementation project The stakeholders are reviewing RFP responses to help make a decision about which project management consulting firm to hire. Given the following information:

Which of the following is the best consulting firm for the company to hire?

A.

Consulting firm 1

B.

Consulting firm 2

C.

Consulting firm 3

D.

Consulting firm 4

A project manager is eager to define access requirements during the initiation phase of a project. Which of the following steps should the project manager perform first?

A.

Define the WBS.

B.

Develop a RAM.

C.

Manage the vendors.

D.

Assess the resource pool.

A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

A.

Ticketing system

B.

Videoconference

C.

Simple messaging system

D.

Corporate social media

Which of the following aspects are true of waterfall as compared to agile? (Select two).

A.

Waterfall is composed of smaller teams working together

B.

Waterfall reinforces customer collaboration

C.

In waterfall, solution validation occurs later in the development cycle.

D.

In waterfall, working software is more of a focus than comprehensive documentation.

E.

Waterfall is less tolerant to changes in scope.

F.

Waterfall is made up of sprints

Which of the following are primary features provided by a standard laaS solution? (Select two).

A.

Encryption

B.

Storage

C.

Networking

D.

User interface

E.

Access

F.

Database

A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?

A.

Dashboard

B.

Gantt chart

C.

Work breakdown structure

D.

Requirements Traceability Matrix

A senior PM is working on the development of a tax application and focuses efforts to create an environment to facilitate and motivate teamwork. The team members seem to be in the storming phase. Which of the following best describes the team life cycle?

A.

The team members are in a conflict that affects their relationship.

B.

The team members perform as a well-organized unit.

C.

The team members have met and are learning about the project.

D.

The team members have completed the work and are moving on from the project.

Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

A.

Approving the change request

B.

Developing a rollback plan

C.

Gathering necessary resources

D.

Defining requirements

After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

A.

Continuous integration

B.

Rollback plan

C.

Customer notification

D.

Automated testing