Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

CompTIA PK0-005 - CompTIA Project+ Certification (2026)

Page: 5 / 14
Total 460 questions

A project manager is meeting with stakeholders to identify objectives and success criteria. Which of the following artifacts is the project manager working on?

A.

Project charter

B.

Requirements traceability matrix

C.

Project communications plan

D.

Project risk register

Given the following velocity chart:

Which of the following updates on the project status should the Scrum master provide to the senior management team?

A.

The project utilized all of its available reserve.

B.

The project has scope creep.

C.

The project deviated from the critical path.

D.

The project is trending ahead of schedule.

A PM wants to add a chart to the monthly status report to show major accomplishments for key events. Which of the following is the best chart to use?

A.

Milestone

B.

Gantt

C.

Burndown

D.

PERT

A company asks some vendors to provide a solution for its specific needs. Which of the following documents should the company provide?

A.

RFP

B.

RFQ

C.

RFB

D.

RFI

A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?

A.

Regression testing

B.

Smoke testing

C.

Stress testing

D.

Automation testing

A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII. Which of the following is the best approach for the project manager to keep the information confidential?

A.

Encryption

B.

Multifactor authentication

C.

Quality assurance

D.

Password protection

Which of the following is available after a project closes and the solution is handed over to the business team and put into production?

A.

Post-implementation support

B.

Audits and inspections

C.

User acceptance testing

D.

Performance testing

Which of the following should be the PRIMARY basis for establishing metrics that measure the effectiveness of an information security program?

A.

Residual risk

B.

Regulatory requirements

C.

Risk tolerance

D.

Control objectives

After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

A.

Continuous integration

B.

Rollback plan

C.

Customer notification

D.

Automated testing

A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?

A.

Rational Unified Process

B.

Waterfall

C.

Agile

D.

DevOps