Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

CompTIA PK0-005 - CompTIA Project+ Certification (2026)

Page: 6 / 14
Total 460 questions

Which of the following best describes a benefit of the CI/CD process?

A.

Software delivery is sped up without compromising quality.

B.

Incremental changes are done at the end of the project.

C.

The software is integrated with other projects easily.

D.

Updates are released every sprint.

A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product. Which of the following charts would BEST prioritize which defects to address?

A.

Pareto

B.

Run

C.

Control

D.

Histogram

A project is not progressing as planned following the departure of the project manager. Which of the following would be the best tool to use to document this information?

A.

Issue log

B.

Risk register

C.

Change log

D.

Defect log

The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?

A.

Data warehouse

B.

SQL database

C.

Multitier architecture

D.

Content management system

During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint. Which of the following individuals should the stakeholder have asked to request the change instead of the team member?

A.

Architect

B.

Project sponsor

C.

Scrum master

D.

Product owner

A project manager distributes minutes after each project meeting. However, the project manager is having difficulties hosting the meetings and documenting the discussions simultaneously. Which of the following should the project manager do in order to be most efficient?

A.

Assign a scribe to take notes.

B.

Record the meeting and transcribe the notes later.

C.

Instruct each team member to take notes.

D.

Get a facilitator for the meetings.

Which of the following best describes a rollback plan?

A.

Apply an alternative plan if the original plan does not work.

B.

Return to the operational state of a system before applying a requested change.

C.

Restart the project with new resources to avoid failures from previous ones.

D.

Repeat the tasks suggested in the requested change until they work.

Which of the following is the best example of CapEx?

A.

Taxes

B.

Vehicles

C.

Salaries

D.

Utilities

Several stakeholders have asked about how the requirements are being covered by the deliverables and the progress of each requirement Which of the following would be the best tool the project manager can use to provide this information to the stakeholders?

A.

Risk register

B.

Change log

C.

Traceability matrix

D.

Project status report

A project manager is responsible for implementing a large, centralized repository that stores raw information from various sources in a structured and organized way. Which of the following should the project manager implement?

A.

Shared folder

B.

Infrastructure

C.

Multitiered architecture

D.

Data warehouse