CompTIA PK0-005 - CompTIA Project+ Certification (2025)
During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following:
Which of the following was the initial cause of the issue?
While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?
A team member needs to make an emergency update. The team member is unable to return to the office. Which of the following is the most secure way to make the update?
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
A meeting agenda included the following items:
. Review the goals of the project.
. Review the progress of the project.
. Discuss if the project is ready to move forward.
Which of the following best describes this type of meeting?
A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.
Which of the following dependencies is most likely happening?
Which of the following is a characteristic that defines a project?
During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?
A stakeholder called a project manager on the telephone to ask for a status report. Which of the following describe this type of communication? (Select two).
A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).