CompTIA PK0-005 - CompTIA Project+ Certification (2025)

Page: 7 / 11
Total 362 questions

During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following:

Which of the following was the initial cause of the issue?

A.

Inadequate memory

B.

Incorrect configuration

C.

Lack of infrastructure

D.

Inadequate instructions

While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?

A.

Perform a root cause analysis.

B.

Organize a stakeholder meeting

C.

Escalate the issue to the CCB

D.

Contact the PMO for assistance.

A team member needs to make an emergency update. The team member is unable to return to the office. Which of the following is the most secure way to make the update?

A.

At home, using home internet and the company’s computer

B.

At a coffee shop, using free Wi-Fi and the corporate computer

C.

At home, using home internet and the corporate virtual private network

D.

Anywhere the team member would like, using a mobile device and mobile internet

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

A.

Critical paths

B.

Resources

C.

Milestones

D.

Work breakdown structures

A meeting agenda included the following items:

. Review the goals of the project.

. Review the progress of the project.

. Discuss if the project is ready to move forward.

Which of the following best describes this type of meeting?

A.

Stand-up

B.

Monthly status

C.

Gap analysis

D.

Gate review

A global shipping slowdown is causing critical raw materials needed for manufacturing to be delivered late. As a result, a project's production run will be delayed from the beginning.

Which of the following dependencies is most likely happening?

A.

Finish-to-start

B.

Start-to-start

C.

Finish-to-finish

D.

Start-to-finish

Which of the following is a characteristic that defines a project?

A.

Will produce a profit

B.

Uses outside resources

C.

Requires a well-defined scope

D.

Has a defined start and finish

During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed. Which of the following should the program manager do next?

A.

Obtain details from the owner of the project.

B.

Update the critical path for the project.

C.

Apply contingency reserves.

D.

Reestimate epic user stories.

A stakeholder called a project manager on the telephone to ask for a status report. Which of the following describe this type of communication? (Select two).

A.

Formal

B.

Internal

C.

Informal

D.

Verbal

E.

Indirect

F.

External

A project manager was just assigned to a new project. Which of the following activities should the project manager undertake after accepting the project? (Select TWO).

A.

Review the detailed plan.

B.

Develop a preliminary scope.

C.

Develop a transition plan.

D.

Develop a project management plan.

E.

Review the resource pool.

F.

Review the project objectives.