CompTIA PK0-005 - CompTIA Project+ Certification (2026)
A project team evaluates the potential risks to a project that uses legacy applications. Which of the following should be the main concern of the project team?
The PM is concerned with multiple copies of the same file causing confusion. Which of the following would prevent this issue?
A project sponsor tells the project manager that new regulatory environment changes are coming in the next month. Which of the following should the project manager do next?
Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?
During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?
A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources. Which of the following risk responses does this demonstrate?
A program manager is reviewing the project portfolio and prioritizing each project based on the company's strategic plan. Which of the following should be considered in this evaluation? (Select TWO).
While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?
A project is not progressing as planned following the departure of the project manager. Which of the following would be the best tool to use to document this information?
A project manager was concerned the results were not fulfilling the expectations at the end of the execution phase. After reviewing the SOW, the project manager realized the vendor delivered everything included in the contract. Which of the following actions should the project manager complete next?