PMI PMI-001 - Project Management Professional v5
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
An associate who calculates fees daily to support the department is doing which of the following?
Which is one of the major outputs of Sequence Activities?
The chart below is an example of a:
Change requests are processed for review and disposition according to which process?
Outputs of the Control Communications process include:
Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?
Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?
Which schedule development technique modifies the project schedule to account for limited resources?
The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:
On what is project baseline development established?
Scope, schedule, and cost parameters are integrated in the:
In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
Which technique helps to determine the risks that have the most potential impact on a project?
An output of the Develop Project Team process is:
Which technique is utilized in the Schedule Control process?
Plan-do-check-act is also known as:
Testing falls into which of the following categories of cost of quality?
Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?