The amount of time that an activity can be delayed from its early start without delaying the project end date is called:

A.

Negative Float

B.

Total Float

C.

Float

D.

c and b

Change requests are made against the ____________?

A.

Project baseline

B.

SOW

C.

Charter

D.

Executive summary

A graphic display of resource usage hours is called a/an_________________.

A.

Organizational chart

B.

Responsibility matrix

C.

WBS

D.

Histogram

Which devises and maintains a worktable scheme to accomplish the business need that the project was undertaken to address.

A.

Development process

B.

Scoping process

C.

Planning process

D.

Information development process

Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components?

A.

Collect Requirements

B.

Initiation

C.

Control Scope

D.

Define Scope

A Project Manager is at the project kick-off meeting. He confidently states the vision and mission for the project. This PM is exhibiting the following leadership style:

A.

Hierarchal

B.

Authoritarian

C.

Charismatic

D.

Associative

An example of a project is:

A.

Billing customers

B.

Managing an organization

C.

Constructing a building

D.

Providing technical support

Which of the following relationship is used in the Arrow Diagramming Method [ADM] :

A.

Start-to-Finish

B.

Finish-to-Start

C.

Start-to-Start

D.

Finish-to-Finish

What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?

A.

Lots of free float

B.

Idle resources

C.

Negative float

D.

Positive float

A scope management plan In which of the following scope management processes is the scope management plan prepared?

A.

Initiation

B.

Collect Requirements

C.

Define Scope

D.

Verify Scope

Project scope is:

A.

The work that must be done in order to deliver a product with the specified features and functions.

B.

The features and functions that are to be included in a product or service.

C.

A narrative description of work to be performed under contract.

D.

a and b

With triangular distribution, the low, likely and high values are 20, 30 and 40, respectively. The mean is _____.

A.

30.0

B.

22.5

C.

25.0

D.

27.5

To calculate the late start and late finish dates for a set of tasks , you must do :

A.

An analysis of the critical path

B.

A forwards pass

C.

A backwards pass

D.

a and g

The closing process scope includes:

A.

Contract closeout

B.

Final reporting

C.

Activity List

D.

Exit interview

Which of the following is ensuring that all features and functions are included in a product or service

A.

Project scope

B.

Project verification

C.

Project control

D.

Product scope