PMI PMI-002 - Certified Associate in Project Management (CAPM) Certification
Information should be communicated to __________.
_________ is the best choice for buyer when the item is well defined.
You are project manager of a project and as part of the team acquisition process; you hire a new employee and assigns him to your project team. According to Maslow's hierarchy of needs, what needs level he most likely is at?
What is the communication channel delta if the members in the communication plan are increased from 5 to 10?
Which is the most risky phase of a project?
You are the project manager of a project. Project is installing AC to hotel rooms. You have done project cost and time estimates, told the customer that the estimates provided will be accurate if the rooms meet the requirements like (wooden coated). This is an example of which of the following?
If a project with a CPI of 1.2, what you tell?
You are the project manager of a project that just went into extinction mode. This means that your project __________.
Which of the following statement is true about project charter?
Which of the following is not part of project scope management?
If a project with a SPI of 1.8, what you tell?
Define Scope involves subdividing the major project deliverables into smaller, more manageable components to __________.
A complete set of indexed project records is called __________.
You are project manager and now in middle of creating RFP (Request for proposal). RFP (Request for proposal) is done in _______.
You are the project manager of the MKTG Project. The project has a budget of $200,000 and is expected to last 2 years. The project is now 20 percent complete and is on schedule. What is the BAC?