_______ is the road map for the execution of the project.

A.

Project plan

B.

sow

C.

WBS

D.

Strategic planning

Conformance to specifications document is one description of _________.

A.

Quality

B.

Scope

C.

Integration

D.

Procurement

Your company create software products, and introducing a new product. To determine the characteristics and features of the new product line, you will have to perform ________.

A.

Progressive elaboration

B.

Stake holder's review

C.

p'an project life cycle

D.

Fast backing

When the version control numbers should change?

A.

Any change occurs

B.

Major changes are made

C.

Any change related to scope only

D.

Only if minor changes are made

Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of ____________.

A.

Enterprise benefits measurement methods when selecting a project

B.

Integral parts of the SOW

C.

Ways to ensure stakeholder commitment

D.

Project selection methods

You are managing a project that will implement a new Insurance software package. Two project team members have difficulty working together. They come to you, for help resolving the issues. You immediately set up a meeting that includes the functional manager. After the meeting you and the functional manager discuss the issues and agree on a solution. What type of organizational structure you are working in?

A.

Functional

B.

Balanced matrix

C.

Piojectized

D.

Strong Matrix

Stakeholder influence is greatest at the ______ of the project.

A.

Beginning

B.

Closing

C.

Controlling

D.

Executing

Project scope is _____________.

A.

The features and functions that are to be included in a product or service

B.

The work that must NOT be done in order to deliver a product with the specified features and functions

C.

Part °ftne project charter

D.

Part of sow

Which monitoring or controlling activities would not result in preventive action being applied?

A.

Control Scope

B.

Manage project team

C.

Quality control

D.

Manage Scope statement

Which of the following is an output of Define Scope?

A.

PBS

B.

Project Scope statement

C.

WBS Template

D.

Constraints

In which phase project manager is assigned to a project?

A.

During the initiation stage

B.

During the planning stage

C.

After approval of budget

D.

After the project is proven feasible

Function of the __________ is to make sure that changes to anything in the project are recorded and agreed to by the stakeholders.

A.

Project Manager

B.

Sponsor

C.

Team Lead

D.

Management

Which of the following are input of close project process?

A.

Project management plan

B.

Contract documentation

C.

Deliverables

D.

Al1 of the above

Delivery dates and availability of resources can be found in the details of the __________.

A.

Work Breakdown Structure

B.

sow

C.

Project Charter

D.

Project Scope Statement

A requirement document is an input of __________ process?

A.

Collect Requirements

B.

Define Scope

C.

Integrated Change Control

D.

Monitor and Control Project Work