PMI PMI-100 - Certified Associate in Project Management (CAPM)®
One of the objectives of a quality audit is to:
A project manager has created an issue log to document issues communicated by project team members during weekly team meetings. This is an input of:
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
Inputs to the Plan Risk Management process include the:
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
Which is an output of the Collect Requirements process?
What are the identified risks for doing excessive decomposition in a WBS?
During which process does the project team receive bids and proposals?
Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project's:
When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:
Which type of probability distribution is used to represent uncertain events such as the outcome of a test or a possible scenario in a decision tree?
At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?
Which Project Time Management process includes bottom-up estimating as a tool or technique?
Those who enter into a contractual agreement to provide services necessary for a project are:
The degree, amount, or volume of risk that an organization or individual will withstand is known as its risk: