Variance and trend analysis is a tool and technique used in which process?

A.

Perform Qualitative Risk Analysis

B.

Perform Quantitative Risk Analysis

C.

Control Risks

D.

Plan Risk Responses

An intentional activity to modify a nonconforming product or product component is called:

A.

defect repair

B.

work repair

C.

corrective action

D.

preventive action

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

A.

Acquire Project Team.

B.

Plan Human Resource Management.

C.

Manage Project Team.

D.

Develop Project Team.

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

A.

project documents updates.

B.

project management plan updates.

C.

change requests.

D.

work performance information.

The chart below is an example of a:

A.

Responsibility assignment matrix (RAM)

B.

Work breakdown structure (WBS)

C.

RACI chart

D.

Requirements traceability matrix

The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule performance index (5PI) for Task 4?

A.

0.83

B.

0.9

C.

1.11

D.

1.33

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

A.

Activity network diagrams

B.

Affinity diagrams

C.

Matrix diagrams

D.

Interrelationship digraphs

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

A.

Critical path method

B.

Critical chain method

C.

Resource leveling

D.

Schedule network analysis

For a stakeholder with low interest and high power, the project manager should:

A.

Monitor the stakeholder.

B.

Manage the stakeholder closely.

C.

Keep the stakeholder satisfied.

D.

Keep the stakeholder informed.

Which is an enterprise environmental factor?

A.

Marketplace conditions

B.

Policies and procedures

C.

Project files from previous projects

D.

Lessons learned from previous projects

The scope management plan and scope baseline are contained in:

A.

organizational process assets

B.

a requirements traceability matrix

C.

the project charter

D.

the project management plan

The process of monitoring the status of the project and product scope as well as managing the changes to the scope baseline is known as:

A.

Validate Scope.

B.

Plan Scope Management.

C.

Control Scope.

D.

Define Scope.

Perform Integrated Change Control is the process of:

A.

Reviewing, approving, and managing all change requests

B.

Facilitating change management, manuals, or automation tools

C.

Comparing actual results with planned results in order to expand or change a project

D.

Documenting changes according to the change control system by the change control board

When the business objectives of an organization change, project goals need to be:

A.

realigned.

B.

performed.

C.

improved.

D.

controlled.

The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

A.

recognition and rewards

B.

compliance

C.

staff acquisition

D.

training needs