Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

A.

Product scope description

B.

Procurement statement of work

C.

Project schedule

D.

Work breakdown structure (WBS)

A tool or technique in Perform Quality Control that a project manager would use is:

A.

quality audits.

B.

process analysis.

C.

benchmarking.

D.

inspection.

The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:

A.

stakeholder management strategy.

B.

communications management plan,

C.

stakeholder register,

D.

performance report.

Which tool or technique is used in Manage Stakeholder Expectations?

A.

Stakeholder management strategy

B.

Communication methods

C.

Issue log

D.

Change requests

Which provides the basic framework for managing a project?

A.

Project life cycle

B.

Work breakdown structure (WBS)

C.

Enterprise environmental factors

D.

Project initiation

Which of the following Project Communication Management processes uses performance reports as an input?

A.

Manage Stakeholder Expectations

B.

Report Performance

C.

Distribute Information

D.

Plan Communications

In which process is a project manager identified and given the authority to apply resources to project activities?

A.

Acquire Project Team

B.

Develop Project Management Plan

C.

Manage Project Execution

D.

Develop Project Charter

The project scope statement and resource calendars are inputs to which Project Time Management process?

A.

Sequence Activities

B.

Estimate Activity Resources

C.

Develop Schedule

D.

Control Schedule

The project manager needs to review the templates in use. The templates are part of the:

A.

Enterprise environmental factors.

B.

Historical information,

C.

Organizational process assets.

D.

Corporate knowledge base.

Which process determines the risks that might affect the project?

A.

Perform Qualitative Risk Analysis

B.

Identify Risks

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

A.

Cost-reimbursable

B.

Time and material

C.

Fixed price or lump-sum

D.

Cost-plus-fixed-fee

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

A.

Applying calendars

B.

Resource leveling

C.

Resource planning

D.

Resource conflict management

Which of the following is an example of the simplest fixed-price contract?

A.

Purchase requisition

B.

Purchase order

C.

Verbal agreement

D.

Request for quote

Which of the following is an input to the Direct and Manage Project Execution process?

A.

Approved change requests

B.

Approved contract documentation

C.

Work performance information

D.

Rejected change requests

Which of the following statements is true regarding project and product lifecycles?

A.

A single product lifecycle may consist of multiple project lifecycles.

B.

A product lifecycle is always shorter than the project lifecycle.

C.

A single product lifecycle can only have one project lifecycle.

D.

A single project lifecycle may consist of multiple product lifecycles.