PMI PMI-100 - Certified Associate in Project Management (CAPM)®
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
A tool or technique in Perform Quality Control that a project manager would use is:
The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:
Which tool or technique is used in Manage Stakeholder Expectations?
Which provides the basic framework for managing a project?
Which of the following Project Communication Management processes uses performance reports as an input?
In which process is a project manager identified and given the authority to apply resources to project activities?
The project scope statement and resource calendars are inputs to which Project Time Management process?
The project manager needs to review the templates in use. The templates are part of the:
Which process determines the risks that might affect the project?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
Which of the following is an example of the simplest fixed-price contract?
Which of the following is an input to the Direct and Manage Project Execution process?
Which of the following statements is true regarding project and product lifecycles?