Which of the following is an input to Develop Human Resource Plan?

A.

Team performance assessment

B.

Roles and responsibilities

C.

Staffing management plan

D.

Enterprise environmental factors

The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:

A.

Control Schedule.

B.

Quality Control.

C.

Perform Integrated Change Control.

D.

Develop Schedule.

The process of identifying the stakeholders' information needs is completed during:

A.

Plan Communications.

B.

Manage Stakeholder Expectations.

C.

Stakeholder Analysis.

D.

Identify Stakeholders.

Which of the following types of a dependency determination is used to define the sequence of activities?

A.

Legal

B.

Discretionary

C.

Internal

D.

Resource

Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:

A.

Conduct Procurements.

B.

Close Procurements.

C.

Administer Procurements,

D.

Plan Procurements.

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?

A.

Perform Quality Control

B.

Perform Quality Assurance

C.

Plan Quality

D.

Report Performance

"Tailoring" is defined as the:

A.

effort of addressing each process to determine which are appropriate and their appropriate degree of rigor.

B.

act of creating a project team with the specialized skills required to produce a required product or service.

C.

action taken to bring a defective or nonconforming component into compliance with requirements or specifications.

D.

adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope.

Which Process Group contains those processes performed to define a new project?

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Documented identification of a flaw in a project component together with a recommendation is termed a:

A.

corrective action.

B.

preventive action.

C.

non-conformance report,

D.

defect repair.

Which of the following documents allows the project manager to assess risks that may require near term action?

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

What does a CPI value greater than 1.0 indicate?

A.

Cost right at the estimated value

B.

Cost under the estimated value

C.

Cost right at the actual value

D.

Cost over the estimated value

During which process would stakeholders provide formal acceptance of the completed project scope?

A.

Perform Quality Control

B.

Verify Scope

C.

Control Scope

D.

Develop Schedule

What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?

A.

Organizational breakdown structure (OBS)

B.

Work performance information

C.

Work package

D.

Work breakdown structure (WBS)

Which process should be conducted from the project inception through completion?

A.

Monitor and Control Project Work

B.

Perform Quality Control

C.

Perform Integrated Change Control

D.

Monitor and Control Risks

Managing procurement relationships and monitoring contract performance are part of which process?

A.

Conduct Procurements

B.

Plan Procurements

C.

Administer Procurements

D.

Close Procurements