PMI PMI-200 - PMI Agile Certified Practitioner (PMI-ACP)
During backlog refinement meeting, the new developer on the team asks the product owner to discuss a new performance threshold requirement and how it impacts the stories in the backlog. What should the team do?
The customer needs assistance in determining the efficiency of a set of process activities within the solution. What should the agile team do?
During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do?
On a complex project with a large degree of uncertainty, the team’s velocity is declining. Upon testing, it is discovered that many of the work items reported as complete are not meeting the stakeholders requirements.
Which of the following could help resolve the incomplete work?
Early in a project stakeholder analysis is performed: however, an organizational restructure redefines key roles What should the project team do?
As part of the organizational change, all project teams within the digital channel’s portfolio have been directed to move from 3-week iterations to 2-week iterations. The development team is frustrated as they think there will not be enough time to test. The product owner does not like this change as it will increase the number of ceremonies.
Which two actions should the scrum master take? (Choose two.)
An agile team lead noticed their team’s velocity was slowing down. They did not deliver a working software during the last iteration and there have been miscommunications between team members.
What should the agile team lead do at the end of this iteration?
Why is stakeholder engagement important for project success?
A technical problem arises that will likely impact the stories planned for delivery in the current sprint What should the scrum master do?
A project manager noticed that a team member had been a consistently high performer until a few months ago. Recently, the team member seems distracted and is not performing well.
How should the project manager handle a review with the team member?
