A legal department representative contacts the scrum master because, while the project's budget has been maintained, it has exceeded its original contracted time and scope What should the scrum master do?

A.

Meet with the team to gain alignment with the legal department's need to stay within the contracted time and scope

B.

Work with the customer to narrow the scope

C.

Share the project's trajectory with the legal department

D.

Meet with the legal department to help them understand that the customer and the team are satisfied with the time and deliverables

During team meetings, the team often struggles with making decisions about their technical approach. What should be done to improve the quality and timeliness of decisions?

A.

Work with the team to improve collaboration by fostering group decision making and conflict resolution techniques.

B.

Promote team discussion but give the product owner the ultimate decision making authority.

C.

Assign individual team members as decision owners for each key decision to avoid conflict.

D.

Identify team members that demonstrate servant leadership qualities to facilitate discussion and make decisions.

A newly formed, colocated team is participating in daily standups, but is otherwise working largely as individual contributors. This has resulted in misalignment of activities. Planned velocity is being met.

What should the agile practitioner do?

A.

Plan activities that will require the team to work collaboratively on a regular basis.

B.

Set collaboration metrics and evaluate individuals against those metrics.

C.

Request that line management add more collaborative team members to the team.

D.

Allow the team to continue with no interference as activities are being met.

What is the first thing an agile development team should do when planning an iteration?

A.

Assign the tasks to one team member.

B.

Separate the stories into tasks.

C.

Estimate the stories' tasks.

D.

Help establish the next sprint's goal.