Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

PMI PMI-ACP - PMI Agile Certified Practitioner (PMI-ACP)

Page: 10 / 15
Total 476 questions

A development team has started working on a new service but is unsure if the service fits the customer's requirements. What should the product owner do to ensure that the service will benefit the customer?

A.

Release the minimum viable product (MVP) to a group of customers and end users for their feedback.

B.

Build a prototype and review it with the targeted customer segment for their feedback.

C.

Invite a group of customers and end users to the biweekly demos to obtain feedback.

D.

Release the prototype of the software for 6 months to a pilot group of customers for feedback.

What should the practitioner do?

A.

Post and discuss rises in the burndown chart

B.

Adjust story points to account for technical debt

C.

Log technical debt as an impediment

D.

Add refactoring tasks to all stories

During an iteration, an urgent customer request for support reaches the team. If they work on it, the team's commitments in this iteration are at risk.

What should the team do next?

A.

Work overtime to meet the customer request and the iteration commitments.

B.

Ask another team that is less busy to handle the situation.

C.

Work with the product owner to assess the impact for reprioritization.

D.

Work on the customer request in the next iteration as a top priority.

What should the agile project manager do?

A.

Since the team has extra time, notify the product owner and secure approval for the extra work on this feature.

B.

Encourage the team to document the improvement and prioritize it for the upcoming iteration, instead of building it now.

C.

Instruct the Scrum Master to have the team use the extra time to complete the extra feature work in the current iteration.

D.

Notify the product owner and have the product owner verify the backlog priority, then encourage team to continue working on the backlog.

A customer has given a project team several requests for new features on a product. The customer is upset that the requests have been placed in the backlog and are not currently being worked on by the team.

What should the team do next?

A.

Review the feature requests and reject the most complex ones.

B.

Organize the feature requests from simple to complex.

C.

Prioritize the requests for the next sprint.

D.

Turn the requests into user stories and prioritize them.

What should the agile practitioner do?

A.

Commend the team on trying the idea, then encourage discussion regarding alternatives

B.

Ask a manager to direct the team on fixing the process

C.

Encourage the team to continue executing the idea to see if it improves

D.

Privately speak with the team member to convey that their idea worsened the outcome

A project manager is working on an agile team. A team member mentions that risks threatening the release date of the current sprint are not being addressed.

What should the project manager do to make sure team members are following up on risks?

A.

Hold one daily coordination meeting to determine the reason team members are not following up on risks.

B.

Ask the team to review the executed tasks and follow up on the upcoming threats.

C.

Display the major risks, assumptions, issues, and dependencies (RAID) log visually to highlight the risk status.

D.

Create one sprint to update and follow up on major release risks.

While reviewing the sprint burndown during a stand-up, the Scrum team identifies that they have fallen behind. Upon further discussion, they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck.

What should the Scrum team do?

A.

For upcoming sprints, have QA team members ensure that their respective skill sets are considered when accepting stories

B.

Have QA team members with the appropriate skill sets spend extra time to help the team succeed

C.

Ensure that QA team members who lack the appropriate skill sets sign up for training within the next few weeks

D.

Ask QA team members experienced with the new automation framework to cross-train the other QA members

A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?

A.

Shared vision statement and sprint goal

B.

Release burnup chart

C.

Velocity metrics

D.

Iteration burndown chart

During a sprint demo, a business representative identifies missing requirements. The agile practitioner realizes that all key stakeholders were not included during requirements detailing.

What should the agile practitioner have done to avoid the situation?

A.

Included the stakeholders in the project planning meeting

B.

Organized an earlier demo to solicit business feedback

C.

Ensured all business leaders signed off on requirements

D.

Engaged key stakeholders periodically to collect requirements