PMI PMI-ACP - PMI Agile Certified Practitioner (PMI-ACP)

Page: 9 / 15
Total 481 questions

The systems integrator for an enterprise resource planning (ERP) project has been onboarded. During an iteration planning session, the team determines that the next highest priority item will take longer than expected to complete in the current sprint.

What should the agile practitioner do next?

A.

Schedule a meeting with the product owner to review the sprint priorities.

B.

Put the high-priority item back into the product backlog.

C.

Extend the sprint end date to accommodate the high-priority item.

D.

Ask the project sponsor to add more resources to ensure timely completion.

A high-profile project team is struggling to meet planned velocity. During a retrospective, the team agreed that their lack of experience in the technology resulted in an excess of rework.

What should be done to resolve this challenge?

A.

Increase the duration of iterations to minimize the frequency of priority changes that are distracting the team.

B.

Reduce the duration of iterations so that the product owner can reprioritize work to ensure business value alignment.

C.

Increase the level of effort in testing to ensure that all defects are identified and properly documented so they can be resolved before the end of the iteration.

D.

Implement a spike to enhance creativity by experimenting with new techniques and process ideas in order to discover more efficient and effective ways of working.

The project lead of an international team noticed that some members were hesitant to express their opinions and thoughts during meetings. What should the project lead do to encourage the team members to express themselves?

A.

Emphasize rules that need to be respected during meetings.

B.

Allow team members to talk when they feel comfortable without any pressure.

C.

Organize separate meetings with each individual team member.

D.

Create a safe environment for discussions during meetings.

In a project to develop a supply-and-demand scenario planning tool, the team aims to streamline development and rapidly deliver features. Which approach best supports quick feature delivery while maintaining quality? (Refer to An Excerpt from the Quality Management Plan)

A.

Implementing a systematic approach to automate integration, testing, and deployment activities

B.

Increasing the frequency of stakeholder meetings to gather feedback on feature priorities

C.

Leveraging regular reviews, feedback loops, and lessons learned to adjust at key milestones

D.

Organizing training sessions for end users to ensure effective utilization of the planning tool

A development team and product owner disagree on a user story in the product backlog. What should the agile practitioner do?

A.

Have the development team follow the product owner ' s direction

B.

Openly challenge the product owner in an effort to poke holes in their approach

C.

Facilitate a conversation about the user story between the development team and the product owner

D.

Serve as a nonpartisan evaluator of each option, and provide direction to the development team and product owner

What should the team do?

A.

Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.

B.

Ask the team lead to calculate the team ' s target velocity according to the project plan, and assign additional resources to increase capacity.

C.

Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.

D.

Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.

An agile coach is guiding a team across multiple locations. They need a united communication approach that involves task-oriented communications and discussion boards with effectiveness.

Which method of communication would be most effective?

A.

Interactive communication

B.

Pull communication

C.

Interpersonal communication

D.

Push communication

During initial planning, a project team investigates several approaches to building new application software, emphasizing the most valuable deliverables. The team needs to convince stakeholders and win their approval.

How can the project team achieve this?

A.

Use a successful platform on which several object-oriented products have been developed in the past.

B.

Create a quick mock-up of the product to serve as a visual tool and adjust it until consensus is reached.

C.

Include brief exploratory iterations, proof-of-concept (POC). to reduce project risk at the beginning of every project cycle.

D.

Deliver an iteration planning diagram, allowing a 2-week refactoring period at the end of the project.

What should the agile coach do?

A.

Work with the team to determine points at which to celebrate its work.

B.

Provide the team with a break by scheduling a team event.

C.

Have the team increase work in progress (WIP) levels to more quickly complete the flow.

D.

Rejuvenate the team by temporarily reducing WIP levels.

HOTSPOT

Organizations that implement agile project management focus on upgrading existing products and services through cost reductions, time savings, or quality enhancements for existing customers (i.e., operational agility). Organizations need to realize that the major financial gains from agile project management will result from the practice of what? (Select answer from dropdown)