Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

PMI PMI-ACP - PMI Agile Certified Practitioner (PMI-ACP)

Page: 8 / 15
Total 476 questions

The project manager has requested that the customer participate in the requirements gathering session for the next release. A conflict comes up regarding the requirements between the customer and team.

What should the project manager do?

A.

Based on value to the organization, the project manager should decide what can be included or not in the final requirements.

B.

The customer is the end user of the product and should have the authority to decide about the product requirements.

C.

The project manager should discuss the requirements with the customer alone so that the team can deliver the prioritized requirements.

D.

Encourage self-organization by communicating the importance of a collaborative approach in decision making about the requirements.

A development team is calculating the number of story points they have completed at the end of an iteration. Although quality assurance (QA) passed and successfully demonstrated one feature, it is not being included in the release package.

Should the team add the feature's story points to their burndown chart?

A.

Yes because the story has been tested and accepted by the business as per the definition of done (Do

B.

Yes, because the development work is complete and quality assurance (QA) and release are external dependencies.

C.

No. any work that is not released cannot be considered complete as per the definition of done (Do

D.

No, because the product owner has not reviewed the release implementation checklist for potential issues.

What should the agile project manager have done to avoid this?

A.

Invited end customers to attend the stand-ups

B.

Organized design review sessions with the customer to obtain sign-off

C.

Held regular meetings with the product owner and project team to elicit detailed business requirements

D.

Conducted frequent review meetings with the customer to continually enhance delivery effectiveness

The product owner is working on an application that will be built in a data lake leveraging a data

integration and transformation software application. With a budget of US$17,000 remaining, how should the product owner allocate the money? (Refer to Exhibit A)

A.

Prioritize the features based on customer feedback and potential value.

B.

Focus on the reporting module since it has the highest estimated cost.

C.

Complete the data repository and reprioritize based on the remaininq budqet.

D.

Proceed with all of the planned features to ensure completeness.

What should the Scrum Master do?

A.

Meet with the team to gain alignment with the legal department's need to stay within the contracted time and scope

B.

Work with the customer to narrow the scope

C.

Share the project's trajectory with the legal department

D.

Meet with the legal department to help them understand that the customer and the team are satisfied with the time and deliverables

During the review session, the product owner discovers that the user interface has a response time of 10 seconds. The non-functional requirements state that it should respond in less than two seconds. The team complains that this requirement was not communicated to them.

What should have been done to avoid this?

A.

A comprehensive user story with all non-functional requirements should have been created

B.

Non-functional requirements should have been added to the acceptance criteria

C.

Non-functional requirements should have been added to the definition of done

D.

A team review of the scope of work should have been conducted

What is the risk of using Agile in a distributed team?

A.

Frequent integration of work produced

B.

Lack of shared knowledge of user stories

C.

Need for more locations to learn Agile

D.

Unclear team structure

What should the team do?

A.

Inform the sponsor about the regional sales manager's disruptiveness and ask that all questions be diverted to the weekly meetings.

B.

Stay focused on the current iteration and let the project manager deal with the regional sales manager's questions.

C.

Invite the regional sales manager to the next iteration review to share the progress.

D.

Create a risk on the risk register to account for some potentially new requirements from the regional sales manager.

An agile coach advised a project manager to continuously improve their ability to support their team and remove any obstacles in the project's way. What role is the agile coach advising to the project manager to take on?

A.

Scrum master

B.

People manager

C.

Servant leader

D.

Squad leader

When working with Lean approaches, which process includes the sequence of steps for delivering value and those required to carry them out?

A.

Value stream mapping

B.

Long-term Lean planning

C.

Business process modeling

D.

Planning poker